Is it possible to add resources of type Cost in Project Plan 365?


Question Link
Answer

Resource type cost is now available in our products!

Please download and install the latest app from link below:
https://www.projectplan365.com/download/

When I assign a user to my business, he will receive an email?
Question Link
Answer
Yes. If he already has an account he will receive an email to join your Business. If the assigned resource doesn't have an account, the user receives also a link inside the email in order to set the password for his new account.
How to Import the Resource pool into my plans?
Question Link
How to Export the resource pool from my plans?
Question Link
How to assign resources to resource pool?
Question Link
Costs in resources does not update in real time when I type in percentage in units
Question Link
Answer
We do recalculation when OK button is pressed on Task Information dialog.
If you need to see how changes of the units impact the cost, please insert Cost column near Resource Name column in grid.
When resource units is changed also the cost value is recalculated.
My project plan does not take limited ressource into account, means 2 tasks remain in parallel with only 1 ressource allocated 100%. How can I plan my project automatically with limited ressources?
Question Link
Answer

Project Plan 365 app will not move your task automatically if you have the same resource on two parallel tasks.

The application tells you that you have an overallocated resource by making the entire resource font with red in Resource Sheet view. If you want tasks to be in sequence, you need to link the tasks and specify a predecessor.

For more information about link/unlink tasks, please read the article below:

https://www.projectplan365.com/articles/link-unlink-tasks/