FAQCategory: ReportsWhat does the Earned Value Over Time chart show in S-Curve report?

What does the Earned Value Over Time chart show in S-Curve report?

1 Answers

The Earned Value Over Time chart shows project’s earned value based on the status date. If actual cost (ACWP) is higher than earned value (BCWP), then the project is over budget.  If planned value (BCWS) is higher than earned value, then the project is behind schedule.