In order to hide the completed tasks, you can apply an Autofilter. In order to do that, follow the steps below:

  1. Go to the Project menu and click on Autofilter option.
  2. Click on the autofilter arrow next to the % complete column heading and uncheck 100% value.
  3. All the completed tasks will be hidden and only the tasks that are in progress will be displayed.

Another way is to apply the Incomplete Tasks filter which will show only the tasks that are in progress and will hide the ones that are completed. In order to apply the Incomplete Tasks filter, go to the Project menu – Filter – Incomplete tasks.