How can I link two tasks?

1 Answers

There are two ways to establish a relationship between two tasks or link two tasks:

  1. Click on the task that will be dependent and go to Task Information – Predecessors – select the task that will dictate the relationship and the type of link between them – click OK.
  2. Enter the ID of the task in the Predecessors/Successors field. You can enter the ID of the predecessor/successor and this automatically creates a Finish-Start link from the predecessor/successor to the current task or you can enter the ID of the predecessor/successor followed by the link type – a value in {SS, SF, FF}.