FAQCategory: TasksHow can I link two tasks?

How can I link two tasks?

1 Answers

To establish a relationship between two tasks or link two tasks click on the task that will be dependent and go to Task Information – Predecessors – select the task that will dictate the relationship and the type of link between them – click OK. 

Another way is to set the enter the ID of the task in the Predecessor field. You can enter the ID of the predecessor and this automatically creates a Finish-Start link from the predecessor to the current task or you can enter the ID of the predecessor followed by the link type – a value in {SS, SF, FF}.