How can I modify the constraint date for a task in grid?
1 Answers
	To modify the constraint date for a task in grid click on the Format menu – Insert column – from Field name select Constraint Date – press OK. Click on a cell and from the date picker drop-down, select the desired Constraint Date.
 
									 
								