FAQ › Category: Scheduling › How can I update Actual Start and Finish Dates of a task using the Update Tasks functionality?

How can I update Actual Start and Finish Dates of a task using the Update Tasks functionality?

1 Answers

On supported Windows and Mac versions of Project Plan 365, select the task and choose Task – Mark on Track – Update Tasks. In the Actual section, enter the Actual Start and/or Actual Finish date, then select OK. The Actual Start field may not be directly editable in the task table.