FAQCategory: ViewsHow can I view how many work hours are assigned to all my subprojects until a certain date?

How can I view how many work hours are assigned to all my subprojects until a certain date?

1 Answers

If you want to see the work hours for all of your subprojects, you can use the Task Usage View. Go to the Task Usage view, collapse all of your subprojects, go to the Format menu – Timescale and from Middle Tier and Bottom Tier tabs, change the units as desired and click OK.

Contact
Chat