FAQCategory: ViewsHow can tasks be added to the Timeline view?

How can tasks be added to the Timeline view?

1 Answers

You can select which tasks from your project will be displayed in the Timeline. Tasks can be added to the Timeline view by double clicking in the empty Timeline area and then selecting the desired tasks from the dialog which appears. Another way to do this is to go to Gantt Chart view, open Task Information dialog for the desired task and then check the “Display on Timeline” option.