FAQCategory: TasksHow do I change a task type ?

How do I change a task type ?

1 Answers

To change a task type, double click on the task name in the Gantt Chart, then in the Task Information dialog, go to Advanced tab and in the Task Type group select Fixed Units, Fixed Work or Fixed Duration and then click OK.