What is Finish to Finish dependency?

1 Answers

The Finish to Finish dependency forces a task to finish only when/after its predecessor is completed; both tasks finish at the same time. If a nonzero lag is present, it is added to the Finish date. For instance, a value of 4FF+2 days in the Predecessors column signifies a Finish – Finish type link with a lag of two days, where the current task has the task with ID = 4 as its predecessor. Note: On Mac and iPad devices, you can also set task dependencies by typing the value in the Successors column.