FAQCategory: Project TrackingWhy is the Late Start Date field different to the Start Date field?

Why is the Late Start Date field different to the Start Date field?

1 Answers

The Late Start Date field represents the latest date an activity can start without affecting the planned project finish date. The Start Date field shows the date when a task is scheduled to begin.