I am not able to change the constraint type of a manual task.
1 Answers
The Constraints Type and the Constraint Date boxes are grayed out for Manual Tasks. Manual Tasks have the main purpose to not have its Start, Finish dates and Duration modified by the Project Plan 365. For this reason, manual tasks should not have any kind of constraints.If you want the app to calculate dates from scheduling inputs, switch the task to automatically scheduled and review the result.