FAQ › Category: Scheduling › How do I change baseline date?

How do I change baseline date?

1 Answers

To change the Baseline dates, using the Gantt Chart view, go to menu Project – Table and select Variance table. Then, you can change the Baseline Start and Finish dates.

Note: Manually editing baseline fields changes the comparison data. Make sure to preserve an original baseline copy if you need an audit trail.