FAQCategory: SchedulingHow can I move a task? It keeps the start date and duration as priority, rather then logic links I am giving with predecessors.

How can I move a task? It keeps the start date and duration as priority, rather then logic links I am giving with predecessors.

1 Answers

​If a task has any actuals applied, such as an actual start date or a percentage of work completed, the task can’t be rescheduled any earlier than the date when the task actually began. If no progress is entered and the task has an inflexible constraint, the constraint can take precedence over task dependencies. Please remove % complete values then try again to change predecessors value.

Contact
Chat