FAQCategory: SchedulingHow can I update the Percent Complete of a task using the Update Tasks functionality?

How can I update the Percent Complete of a task using the Update Tasks functionality?

1 Answers

To update the Actual Duration of a task, go to menu Tasks – Mark on Track – Update Tasks. In the Update Tasks dialog set the desired value in the %Complete: field then click OK for the changes to be applied.
Note: When you specify the percentage of completion for a task, Project calculates the actual duration and remaining duration according to the formulas Actual Duration = Duration * Percent Complete and Remaining Duration = Duration – Actual Duration.

Contact
Chat