How do I compare planned dates with progress to date?

1 Answers

Save a baseline before tracking begins, record progress using fields supported by the app, and compare the current schedule with the baseline in Tracking Gantt or the Variance table. A baseline is the planned reference; it is not a substitute for entering actual progress.