How to level the entire project?
1 Answers
To level the entire project, go to “Team” menu and click the “Level All” button. In the “Resource Leveling” dialog, the “Entire Project” option and click the “OK” button. A summary of how Project Plan 365 fixed the overallocation will be displayed. Click the “OK” button for the changes to be applied. For detailed information about Resource Leveling, see the Resource Leveling Online Help Article.