FAQCategory: SchedulingI changed the start date of my project from Project Information dialog but the dates are the same.

I changed the start date of my project from Project Information dialog but the dates are the same.

1 Answers

If you are trying to change the start date of your project but it doesn’t work it is because in your project you have some tasks that have constraints applied. If you don’t want to remove the constraints in the project, you can use the “Move Project” functionality in the Project menu in order to change the Start Date of your project.