FAQCategory: TasksIs there a way to take my existing manually scheduled tasks and edit them all at once to change them all to automatically scheduled?

Is there a way to take my existing manually scheduled tasks and edit them all at once to change them all to automatically scheduled?

1 Answers

A quick way to change the Task Mode for multiple tasks is to insert the Task Mode column in Gantt Chart view, then you can set the task mode to automatically schedule for the first 4 tasks for example. Then copy (CTRL+C) the 4 cells and paste (CTRL+V) them below.