FAQCategory: TasksMy project plan does not take limited ressource into account, means 2 tasks remain in parallel with only 1 ressource allocated 100%. How can I plan my project automatically with limited ressources?

My project plan does not take limited ressource into account, means 2 tasks remain in parallel with only 1 ressource allocated 100%. How can I plan my project automatically with limited ressources?

1 Answers

Project Plan 365 app will not move your task automatically if you have the same resource on two parallel tasks. 

The application tells you that you have an overallocated resource by making the entire resource font with red in Resource Sheet view.

If you want tasks to be in sequence, you need to link the tasks and specify a predecessor.