How to level manually the resources?
Question Link
Answer
We are sorry, but the resource leveling feature is not available in our application at this point.
Can Project Plan 365 solve automatically the resource overallocation?
Question Link
Answer
Project Plan 365 app will not move your task automatically if you have an overallocated resource on two parallel tasks.
The application tells you that you have an overallocated resource by making the entire resource font with red in Resource Sheet view.
In order to solve the overallocation, you need to link the tasks and specify a predecessor.
How do I know due tasks not completed?
Question Link
Answer
In order to see the tasks that are not completed, please look at %Complete field. All the tasks that have other value than 100 are not completed yet.

I would like to know how to compare 2 projects?


Question Link
Answer

You can compare two projects by going to menu Report and press on Compare button.A comparison report contains only the differences between the two versions. It is not a consolidation of the two projects.This utility does not compare assignments. It compares tasks and resources only.

Can I create a link between tasks in different subprojects?
Question Link
Answer
At this moment you can only view an external task created with MS Project.
Can I insert multiple resources on iPad?
Question Link
Answer
We are sorry, but the multiple selection feature is not available on iOS at this point.
Why should I use a password protected file?
Question Link
Answer
In order to prevent an accidental open of your project, you can add a password to the file. You can open this plan in Project Plan 365 application.
What does the “Compare” functionality do?
Question Link
Answer
The "Compare" functionality allows reviewing differences between the current version and an earlier or later version of the same project.You can also use this tool to review a current version of a project and one or more projected versions of the same project reflecting different possible scenarios. This may prove useful when evaluating different possible outcomes and potential shortcomings to arise in the future based on the current status.
Custom views created with Project Plan 365 compatible with MS Project?
Question Link
Answer
Project Plan 365 can save up to 5 Gantt Chart based custom views that are compatible with MS Project.
How to edit a custom view?
Question Link
Answer
To edit a created custom view, go to More Views, select desired custom view click on the “Edit” button and change details for your custom view.
How do I create a custom view?
Question Link
Answer
To create a custom view, go to More Views, click on the “New” button and fill-in the details for your custom view.
How many custom views can I create with Project Plan 365?
Question Link
Answer
Project Plan 365 supports up to 5 Gantt Chart based custom views.
Why and when to use a custom view?
Question Link
Answer
A custom view may come in handy when you do not want to modify the standard Gantt Chart by adding customization, alter the table, etc. Think when multiple people work on the same project and they all have different needs and preferences - you just go on and create a custom Gantt Chart that fits your needs and speedup your project analysis process while maintaining the other views clean.
What is a custom view?
Question Link
Answer
A custom view is a Gantt Chart based view, that supports various customization (name, table, filter, group, styles) while keeping the standard Gantt Chart unchanged.
What does the Task Burndown chart show in the Burndown report?
Question Link
Answer
The Task Burndown chart shows a comparison of the number of tasks finished, the number of remaining tasks and the baseline estimate of how many tasks would be finished at this point in the project.
What does the Work Burndown chart show in the Burndown report?
Question Link
Answer
The Work Burndown chart shows a comparison of how much work is finished, how much work is scheduled to be finished and the baseline estimate of how much work would be completed at this point in the project.
What charts are available in the Burndown report?
Question Link
Answer
In Burndown report are available two charts: Work Burndown and Task Burndown.
What does the “Burndown” report?
Question Link
Answer
The "Burndown" report is a visual representation of work left to do versus time. It gives you the project status by comparing the planned, completed and remaining work on a chart, based on your current project data.
What is a password protected file?
Question Link
Answer
Password protected files are files which in order to be opened require authentication via password.
What is a resource calendar?
Question Link
Answer
Resource calendars are normal calendars that ensure the resources are scheduled only when they are available for work. You can change working time or nonworking time for e set of resources at any time.
What does the “Resource Information” functionality do?
Question Link
Answer

The Resource Information as the name describes it, allows to view basic information about the selected resource and the resource's availability and also you can change the resource name, Initials, Group, or Code for the selected resource.

My project plan does not take limited ressource into account, means 2 tasks remain in parallel with only 1 ressource allocated 100%. How can I plan my project automatically with limited ressources?
Question Link
Answer

Project Plan 365 app will not move your task automatically if you have the same resource on two parallel tasks. 

The application tells you that you have an overallocated resource by making the entire resource font with red in Resource Sheet view.

If you want tasks to be in sequence, you need to link the tasks and specify a predecessor.

Where can I set a Group for my resource?
Question Link
Answer
​To set a group for your resource click on the desired resource - Resource menu tab - Resource Information - General - Group.​
Where can I find more information about a resource?
Question Link
Answer
​To view more detailed information about a resource, in any resource view (Resource Sheet, Resource Usage, or Resource Graph), click the resource, and then click Resource Information.​
How do I assign a resource to a summary task?
Question Link
Answer

In the Gantt Chart, go to the Resource Names column. Click on the arrow and pick the resources to work on the task.