How do I change the start and finish dates of a task by dragging the taskbar?
How do I change the start and finish dates of a task by dragging the taskbar?
Question Link
Question Link
Answer
To change the start and finish dates of a task directly from the Gantt Chart, locate in the chart area the task bar corresponding to the task that you want to adjust its start and finish date and drag the task bar to the left or right as you desire. During the dragging process, a virtual taskbar will be shown, guiding you through the change step.
How do I change the relationship between tasks from the Gantt Chart?
How do I change the relationship between tasks from the Gantt Chart?
Question Link
Question Link
How do I add relationships between tasks directly on the Gantt Chart?
How do I add relationships between tasks directly on the Gantt Chart?
Question Link
Question Link
What actions can I perform directly on the Gantt Chart?
What actions can I perform directly on the Gantt Chart?
Question Link
Question Link
Can I export the Cashflow report to csv/excel?
Can I export the Cashflow report to csv/excel?
Question Link
Question Link
What is Timephased data?
What is Timephased data?
Question Link
Question Link
Can task types be used to change the hierarchical structure of a task?
Can task types be used to change the hierarchical structure of a task?
Question Link
Question Link
What is Fixed Duration Task Type?
What is Fixed Duration Task Type?
Question Link
Question Link
What is Fixed Work Task type?
What is Fixed Work Task type?
Question Link
Question Link
What is Fixed Units Task Type?
What is Fixed Units Task Type?
Question Link
Question Link
What does the “Set Task Type” functionality do?
What does the “Set Task Type” functionality do?
Question Link
Question Link
Answer
The “Set Task Type” functionality, as the name indicates, allows you to change the types of automatically-scheduled tasks. The available task types are: fixed units, fixed work, and fixed duration. Project looks at a task's type to determine how duration, work, and units will behave as Project schedules your project.
How to change the Task Mode for a task?
How to change the Task Mode for a task?
Question Link
Question Link
Answer
To change the Task Mode, click in the Task Mode field. In the list that appears, click Manually Scheduled or Auto Scheduled. You can also select specific tasks, then in the Task Information dialog under Task menu, General tab, in the Schedule Mode group, select Manually Scheduled or Auto Scheduled and click OK.
What are manually scheduled tasks?
What are manually scheduled tasks?
Question Link
Question Link
Answer
Manual tasks are tasks with task mode manually scheduled. They should be used when you want to explicitly set a task's start and finish dates and not allow it to be changed automatically by the scheduler based on changes to other tasks. When a task is in manually scheduled mode, the Start, Finish, and Duration columns can be blank or include text values in addition to recognizable dates.
What are automatically scheduled tasks?
What are automatically scheduled tasks?
Question Link
Question Link
What does the “Set Task Mode” functionality do?
What does the “Set Task Mode” functionality do?
Question Link
Question Link
Answer
The “Set Task Mode” functionality gives you the option of deciding how much control you want over task scheduling in a project. The Task Mode field indicates whether a task is scheduled manually or automatically scheduled. By default, tasks are set as auto scheduled, with a start date, finish date, and duration calculated based on inserted fields values.
How to enter a material resource in Resource Sheet view?
How to enter a material resource in Resource Sheet view?
Question Link
Question Link
How do I set start finish date hours?
How do I set start finish date hours?
Question Link
Question Link
Answer
Before starting to schedule your project by setting start and finish dates, you can use the Date Format option on the File menu in the Options dialog box to specify the date format used to display information in date fields. For a task you can enter the time and the date in any order or you can use calendar picker to select desired date and hour.
What does the “Set start finish date hours” functionality do?
What does the "Set start finish date hours" functionality do?
Question Link
Question Link
How do I change task scheduling options defaults for days, weeks, and months?
How do I change task scheduling options defaults for days, weeks, and months?
Question Link
Question Link
What does the “Change task scheduling options defaults for days, weeks, and months?” functionality do?
What does the “Change task scheduling options defaults for days, weeks, and months?” functionality do?
Question Link
Question Link
Answer
The “Change task scheduling options defaults for days, weeks, and months” functionality, as the name describes it, allows to make changes in the tasks scheduling settings to indicate how much time you want to constitute a day, a week, and a month when entering and reviewing durations in a task view. It can also help you synchronize task scheduling with what you've established in the working time calendars for resource.
How do I exit the full screen mode?
How do I exit the full screen mode?
Question Link
Question Link
How do I change the font settings for all the tasks or for a particular type?
How do I change the font settings for all the tasks or for a particular type?
Question Link
Question Link
How do I delete a task from my project?
How do I delete a task from my project?
Question Link
Question Link
Does deleting a task affect the project schedule?
Does deleting a task affect the project schedule?
Question Link
Question Link
Answer
Deleting a task from your project may affect your schedule and you may run into problems. If you have started tracking actual work for your project, don't remove tasks that have actual work or other tracking data associated with them, or you'll lose valuable historical project information. If you delete a summary task, either being collapsed or expanded, all of its subtasks are also deleted. After you delete a task, the application automatically renumbers the remaining tasks.
Does deleting a resource affect the project schedule?
Does deleting a resource affect the project schedule?
Question Link
Question Link
Answer
Deleting a resource from your project may affect your schedule and you may run into problems. The resource assignments involving a resource are also removed from the tasks in your project: deleting a resource means any assignments you’ve made are gone as well, such that you run the risk of orphaning tasks without anyone to perform them. Costs could change: when you remove a resource from a task, the application deletes any actual costs associated with the resource