FAQ Project Plan 365

Browse by Category

How can I copy a table?
Question Link
Answer

In order to copy an existing table, go to menu Project - Tables - More Tables. Select the desired table that you want to copy and click on the Copy button. Insert the new name and make the formatting changes you desire and click on the OK button.

On what platforms can I create or copy a table?
Question Link
Answer

You can create or copy a table on Windows, Mac and iOS platforms.

How can I customize a table in the app?


Question Link
Answer

To customize a table in Project Plan 365, click on the “Table” option under the “Project” menu and then choose the “More tables” option. Then choose the “Edit” option to make the changes you need.

What are the Resource Tables available in the app?


Question Link
Answer

The Resource Tables are: Cost, Earned Value, Entry - Material Resources, Entry - Work Resources, Earned Value Cost Indicators, Entry, Export, Hyperlink, Summary, Usage, Work.

What are tables?
Question Link
Answer

The "Tables" functionality allows you to see some specific information about tasks, resources, and assignments in a sheet view. You can use predefined tables to show only the fields you want, or you can create your own tables.

When can be used the Project Information dialog?


Question Link
Answer

The Project Information can be used when your plans change, you can change this initial project information at any time in the Project Information dialog box. However, if you have applied actual data, such as actual start or finish dates, to tasks, the tasks will not be rescheduled based on the updated project information. In addition, if you have put constraints on tasks, moving the project's start or finish date won't necessarily move all tasks relative to the new date.

How do I sort tasks by date?
Question Link
Answer

To sort tasks go to the Gantt Chart view and click on the Project menu. Click Sort - Sort By. Choose the desired settings and click Sort.

What is Sort?


Question Link
Answer

The “Sort” functionality arranges task or resource in the current view, based on the specified criteria. Tasks can be sort by multiple columns at the same time, sort tasks by date, sort tasks by resources or sort by other tasks properties.

What are the Current Activities filters?
Question Link
Answer

The Current Activities filters are: Active Tasks, Completed Milestones, Completed Tasks, Current Sprint Remaining Tasks, In Progress Assignments, In Progress Tasks, Incomplete Tasks, Late Milestones, Late Tasks, Milestones Due This Month, No Actuals, Remaining Tasks in Board, Select Sprint, Selected Sprint, Should Start By..., Should Start/Finish By..., Slipped/Late Progress, Slipping Assignments, Slipping Tasks, Sprint Planning, Tasks Due This Week, Tasks Starting Soon, Unstarted Assignments, Unstarted Tasks, Upcoming Milestones.

What are the Costs filters?
Question Link
Answer

The Costs filters are: Work Complete, Work Incomplete, Cost Greater Than..., Cost Overbudget, Late/Overbudget Tasks Assigned To…, Work Overbudget.

What are the Assignments filters?
Question Link
Answer

The Assignments filters are: No Resource Assigned, Overallocated Tasks, Overallocated Resources, Resource Cost, Resource Material, Resource Work, Resource with Attachments,  Summary Task with Assigned Resources, Tasks/Assignments with Overtime, Using Resource in Date Range…, Using Resource.

What are the Overview filters?
Question Link
Answer

The Overview filters are: All Tasks, All Resources, Created after…, Critical, Current Sprint, Date Range…, Group, Manually Scheduled Tasks, Milestones, Resource Group…, Resource Range, Summary Tasks, Task Board Tasks, Task Range…, Tasks with a Task Calendar Assigned, Tasks with Deadlines, Tasks with Duration <8, Tasks with Estimated Durations, Tasks with Fixed Dates, Tasks without Dates, Top Level Tasks.

What does the "Backlog" filter do?
Question Link
Answer
This filter displays the tasks before being prioritized (example: Not started, Done, In progress, Next Up).
What does the "Remaining Tasks in Board" filter do?
Question Link
Answer
This filter represents a snapshot of the current sprint backlog allowing everyone to see which tasks remain to be started, which are in progress and which are done.
What is Status Date field?
Question Link
Answer
Represents the date set to report the project’s progress.
What is Company field?
Question Link
Answer
Contains company name.
What is Title field?
Question Link
Answer
Shows the project name
What is Subject field?
Question Link
Answer
Contains project subject.
What is Manager field?
Question Link
Answer
Indicates the project owner.
What is Keywords field?
Question Link
Answer
Contains document keywords.
What is Comments field
Question Link
Answer
Contains project notes.
What is Calendar field?
Question Link
Answer
Indicates which calendar is the default base calendar for tasks and resource calendars.
How do I change the appearance of nonworking time on Team Planner view?
Question Link
Answer
To change the appearance of nonworking time on Team Planner view, right-click on a blank area of the right side of the view (not on a task), and then click Nonworking Time.
How do I view more or less detail in Team Planner view?
Question Link
Answer
Use the Zoom options to change how much time is displayed on the right side of the view.
What indicates the color of the tasks in Team Planner view?
Question Link
Answer
The color of the task gives you useful information about its scheduling state. For example, portions of the bar that are dark blue indicate actual work. Green tasks are manually scheduled.
Contact
Chat