What does the "Late Tasks" filter do?
Question Link
Answer
The "Late Tasks" filter allows seeing all the tasks that are finishing after the finish date in the baseline plan.
What does the "Late Milestones" filter do?
Question Link
Answer
The "Late Milestones" filter allows seeing all the milestone tasks that are finishing after the finish date in the baseline plan.
What does the "Incomplete Tasks" filter do?
Question Link
Answer
The "Incomplete Tasks" filter allows seeing all tasks that are not completed.
What does the "In Progress Tasks" filter do?
Question Link
Answer
The "In Progress Tasks" filter allows seeing all tasks that are started but not completed yet.
What does the "Current Sprint Remaining Tasks" filter do?
Question Link
Answer
The "Current Sprint Remaining Tasks" filter allows seeing tasks from the current sprint with percent complete <0.
What does the "Completed Tasks" filter do?
Question Link
Answer
The "Completed Tasks" filter allows seeing all tasks that are finished.
What does the "Completed Milestones" filter do?
Question Link
Answer
The "Completed Milestones" filter allows you to see the milestone tasks that are finished.
What does the "Active Tasks" filter do?
Question Link
Answer
The "Active Tasks" filter allows you to see all the tasks that are active.
What does the "Top Level Tasks" filter do?
Question Link
Answer
The "Top Level Tasks" filter allows seeing the highest-level summary tasks.
What does the "Tasks without Dates" filter do?
Question Link
Answer
The "Tasks without Dates" filter allows seeing the manual tasks without start/finish date value inserted.
What does the "Tasks with Fixed Dates" filter do?
Question Link
Answer
The "Tasks with Fixed Dates" filter allows seeing all tasks that have an actual start date.
What does the "Tasks with Estimated Durations" filter do?
Question Link
Answer
The "Tasks with Estimated Durations" filter allows seeing all tasks where duration is estimated.
How do I apply the "Tasks with Duration <8" filter?
Question Link
Answer
In order to apply the "Task with Duration <8" filter, go to menu Project - Filter and select More Reports then select Tasks with Duration <8 and click on Apply button.
What does the "Tasks with Duration <8" filter do?
Question Link
Answer
The "Tasks with Duration <8" filter allows seeing all tasks where task duration is less than 8 hours.
What does the "Tasks with Deadlines" filter do?
Question Link
Answer
The "Tasks with Deadlines" filter allows seeing all tasks where a deadline was specified.
What does the "Tasks with Attachments" filter do?
Question Link
Answer
The "Tasks with Attachments" filter allows seeing all tasks where a note or object was attached.
What does the "Tasks with a Task Calendar Assigned" filter do?
Question Link
Answer
The "Tasks with a Task Calendar Assigned" filter allows seeing all tasks where a task calendar was applied.
What does the "Task Range..." filter do?
Question Link
Answer
The "Task Range..." filter allows seeing all tasks that have ID numbers within the specified range.
What does the "Task Board Tasks" filter do?
Question Link
Answer
The "Task Board Tasks" filter allows seeing all tasks created using Scrum methodology.
What does the "Summary Tasks" filter do?
Question Link
Answer
The "Summary Tasks" filter allows seeing all tasks that have subtasks.
What does the "Resource Group..." filter do?
Question Link
Answer
The "Resource Group..." filter allows seeing the tasks allocated to the resources belonging to a specified group.
How do I apply the "Milestones" filter?
Question Link
Answer
In order to apply the "Milestones" filter, go to menu Project - Filter and select Milestones or select More Reports then select Milestones and click on Apply button.
What does the "Milestones" filter do?
Question Link
Answer
The "Milestones" filter allows seeing only the tasks that are milestones.
What does the "Manually Scheduled Tasks" filter do?
Question Link
Answer
The "Manually Scheduled Tasks" filter allows seeing all the manually scheduled tasks.
What does the "Linked Fields" filter do?
Question Link
Answer
The "Linked Fields" filter allows seeing the tasks to which information from other programs has been linked.