FAQ Project Plan 365

Browse by Category

What is Linked Fields field?
Question Link
Answer
The Linked Fields field indicates whether there are OLE links to the task, resource, or assignment, either from elsewhere in this project file, from another Microsoft Project file, or from another program.
What is Leveling Delay field?
Question Link
Answer
The Leveling Delay field contains the time that a task or assignment is to be delayed from its early start date because of resource leveling.
What is Leveling Can Split field?
Question Link
Answer
The Leveling Can Split field indicates whether the resource leveling function can cause splits on remaining work on this task.
What is Level Assignments field?
Question Link
Answer
The Level Assignments field indicates whether the leveling function can delay and split individual assignments (instead of the whole task) in order to resolve overallocations.
What is Late Start field?
Question Link
Answer
The Late Start field contains the latest date that a task can start without delaying the finish of the project.
What is Late Finish field?
Question Link
Answer
The Late Finish field contains the latest date that a task can finish without delaying the finish of the project.
What is Initials field?
Question Link
Answer
The Initials field shows the abbreviation for a resource name.
What is Indicators field?
Question Link
Answer
The Indicators field displays indicators that give different types of information about a task or resource.
What is Inactive field?
Question Link
Answer
Enterprise resources are not deleted. Instead, they are made inactive by a user who has administrative rights.
What is Import field?
Question Link
Answer
The Import field specifies whether a resource should be imported into Project Server as an enterprise resource. It is part of the Import Resources Wizard.
What is Ignore Warnings field?
Question Link
Answer
When Microsoft Project detects a potential scheduling conflict with a manually scheduled task, it generates a warning and the field containing the problem data is underlined in red. The Ignore Warnings field indicates whether you have chosen to hide the schedule conflict warning indicator.
What is Ignore Resource Calendar field?
Question Link
Answer
The Ignore Resource Calendar field indicates whether the scheduling of the task considers the calendars of the resources assigned to the task.
What is ID field?
Question Link
Answer
The ID field contains the identifier number that Project automatically assigns to each task or resource as you add them to the project.
What is Hyperlink SubAddress field?
Question Link
Answer
The Hyperlink SubAddress field contains the specific location in a document in a hyperlink associated with a task, resource, or assignment.
What is Hyperlink Href field?
Question Link
Answer
The Hyperlink Href field contains the combination, or concatenation, of the Hyperlink Address and Hyperlink SubAddress fields associated with a task, resource, or assignment.
What is Hyperlink field?
Question Link
Answer
The Hyperlink field shows the title or explanatory text for a hyperlink associated with a task, resource, or assignment.
What is Hyperlink Address field?
Question Link
Answer
The Hyperlink Address field contains the address for a hyperlink associated with a task, resource, or assignment.
What is Hide Bar field?
Question Link
Answer
The Hide Bar field indicates whether the Gantt bars and Calendar bars for a task are hidden.
What is Health field?
Question Link
Answer
The Health field contains the current status or condition, such as Early or Completed, of the current task as selected in the Health lookup table, which is shipped with Microsoft Project Server and can be modified to reflect an organization’s specific status measures.
What is Group field?
Question Link
Answer
The Group field contains the name of the group that a resource belongs to.
What is Group By Summary field?
Question Link
Answer
The Group By Summary field indicates whether this row in the task or resource sheet is the summary row for tasks or resources grouped by a particular category.
What is Goals field?
Question Link
Answer
The Goals field contains the measurable goals of the current proposal. This field is controlled by the workflow.
What is Generic field?
Question Link
Answer
The Generic field indicates whether a resource is generic or not.
What is Flag1-20 field?
Question Link
Answer
The Flag1 through Flag20 fields indicate whether a task, resource, or assignment is marked for additional action or identification of some kind.
What is Fixed Cost field?
Question Link
Answer

A Fixed cost is a cost that is set for a task and not for a resource. A fixed cost remains constant regardless of the task duration, the amount of work that is performed by the resource, and the number of assignment units.

Contact
Chat