What is Baseline1-10 Finish field?
Question Link
Answer
The Baseline1 through Baseline10 Finish fields store the planned completion date for a task or resource assignment at the time that you save a corresponding baseline.
What is Baseline1-10 Duration field?
Question Link
Answer
The Baseline1 through Baseline10 Duration fields store the span of time planned to complete a task.
What is Baseline1-10 Deliverable Start field?
Question Link
Answer
The Baseline1 through Baseline10 Deliverable Start fields contain the planned deliverable start dates saved with the corresponding project baselines.
What is Baseline1-10 Deliverable Finish field?
Question Link
Answer
The Baseline1 through Baseline10 Deliverable Finish fields contain the planned deliverable finish dates saved with the corresponding project baselines.
What is Baseline1-10 Cost field?
Question Link
Answer
The Baseline1 through Baseline10 Cost fields store the total planned cost for a task, a resource, or an assignment.
What is Baseline1-10 Budget Work field?
Question Link
Answer
The Baseline1 through Baseline10 Budget Work fields store the originally planned budget work amounts for work resources and material resources that are specifically identified as budget resources.
What is Baseline1-10 Budget Cost field?
Question Link
Answer
The Baseline1 through Baseline10 Budget Cost fields store the originally planned budget cost amounts for cost resources that are specifically identified as budget resources.
What is Baseline0-10 Remaining Tasks field?
Question Link
Answer
The Baseline0 through Baseline10 Remaining Tasks fields contain the number of scheduled subtasks that remained to be completed on a given day for a summary task, when the baseline was set. They also contain the number of scheduled tasks that remained to be completed on a given day for a subproject, when the baseline was set.
What is Baseline0-10 Remaining Cumulative Work field?
Question Link
Answer
The Baseline0 through Baseline10 Remaining Cumulative Work fields contain the remaining amount of time scheduled for all resources assigned to tasks, when the baseline was set.
What is Baseline0-10 Estimated Start field?
Question Link
Answer
When you set a baseline, Microsoft Project copies the Scheduled Start dates for a task or assignment and stores them in the Baseline Estimated Start fields (Baseline Estimated Start to Baseline1 Estimated Start through Baseline10 Estimated Start). This is true whether the tasks are manually or automatically scheduled.
What is Baseline0-10 Estimated Finish field?
Question Link
Answer
When you set a baseline, Microsoft Project copies the Scheduled Finish dates for a task or assignment and stores them in the Baseline Estimated Finish fields (Baseline Estimated Finish to Baseline1 Estimated Finish through Baseline10 Estimated Finish). This is true whether the tasks are manually or automatically scheduled.
What is Baseline0-10 Estimated Duration field?
Question Link
Answer
The Baseline0-10 Estimated Duration fields show the approximated span of time planned to complete a task. When you set a baseline, Microsoft Project copies the Scheduled Duration values for tasks and stores them in the Baseline Estimated Duration fields (Baseline Estimated Duration to Baseline1 Estimated Duration through Baseline10 Estimated Duration). This is true whether the tasks are manually or automatically scheduled.
What is Baseline0-10 Cumulative Work field field?
Question Link
Answer
The Baseline0 through Baseline10 Cumulative Work fields contain the amount of time scheduled for all resources assigned to tasks, accumulated over time, when the baseline was set.
What is Baseline Work field?
Question Link
Answer
The Baseline Work field shows the total planned person-hours scheduled for a task, resource, or assignment.
What is Baseline Start field?
Question Link
Answer
The Baseline Start field shows the planned start date for a task or assignment at the time that you saved a baseline.
What is Baseline Finish field?
Question Link
Answer
The Baseline Finish field shows the planned completion date for a task or assignment at the time that you saved a baseline.
What is Baseline Duration field?
Question Link
Answer
The Baseline Duration field shows the original span of time planned to complete a task.
What is Baseline Deliverable Start field?
Question Link
Answer
The Baseline Deliverable Start field contains the originally planned deliverable start date saved with the project baseline.
What is Baseline Deliverable Finish field?
Question Link
Answer
The Baseline Deliverable Finish field contains the planned deliverable finish date saved with the project baseline.
What is Baseline Cost field?
Question Link
Answer
The Baseline Cost field shows the total planned cost for a task, a resource for all assigned tasks, or for work to be performed by a resource on a task.
What is Baseline Budget Work field?
Question Link
Answer
The Baseline Budget Work field displays the originally planned budget work amounts for budget work and material resources. Budget resources are assigned only to the project summary task.
What is Baseline Budget Cost field?
Question Link
Answer
The Baseline Budget Cost field displays the originally planned budget for budget cost resources. Budget resources are assigned only to the project summary task.
What is Base Calendar field?
Question Link
Answer
The Base Calendar field indicates which calendar is the base calendar for a resource calendar.
What is Available To field?
Question Link
Answer
The Available To field shows the end date that a resource is available for work at the units specified for the current time period.
What is Available From field?
Question Link
Answer
The Available From field shows the starting date that a resource is available for work at the units specified for the current time period.