FAQ Project Plan 365
Browse by Category
How do I add text to a type of bars in Gantt Chart?
How do I add text to a type of bars in Gantt Chart?
Question Link
Question Link
How do I change the color, shape, or pattern of Gantt bars?
How do I change the color, shape, or pattern of Gantt bars?
Question Link
Question Link
What does the “Bar Styles” functionality do?
What does the “Bar Styles” functionality do?
Question Link
Question Link
What is the difference between Assignment and Time Phased Assignment Fields?
What is the difference between Assignment and Time Phased Assignment Fields?
Question Link
Question Link
Answer
Assignment fields show information for each assignment. Assignment fields can be displayed in the sheet portion of the Task Usage and Resource Usage views Time Phased assignment fields show information for each assignment as distributed over its duration. Time Phased assignment fields can be displayed in the time phased portion of the Resource Usage and Task Usage Views.
What is the difference between Resource and Time Phased Resource Fields?
What is the difference between Resource and Time Phased Resource Fields?
Question Link
Question Link
Answer
Resource fields show information for each resource, including summarized information on all tasks assigned to each resource. Resource fields can be displayed in the resource views such as the Resource Sheet and Resource Usage views. Time Phased resource fields show information for each resource as distributed over the duration of resource availability on the project. Time Phased Resource fields can be displayed in the time phased portion of the Resource Usage View.
What is the difference between Task and Timephased Task Fields?
What is the difference between Task and Timephased Task Fields?
Question Link
Question Link
Answer
Task fields show task-related information and can be displayed in the task views such as the Gantt Chart, Task Sheet, and Network Diagram views. Time Phased task fields show information for each task as distributed over its duration. Time Phased task fields can be displayed in the Time Phased portion of the Task Usage View.
How can I see the Total Slack field for my tasks?
How can I see the Total Slack field for my tasks?
Question Link
Question Link
When should I use the Total Slack field?
When should I use the Total Slack field?
Question Link
Question Link
Answer
Use the Total Slack field to determine whether the task has any time available for a delay. This can be useful if a resource needs more time on a task, or if you want to assign a resource to another task. You can also use the Total Slack field to determine how to recover a schedule that's slipping.
What is a “link” between tasks?
What is a “link” between tasks?
Question Link
Question Link
How can I see the Late Finish date for tasks?
How can I see the Late Finish date for tasks?
Question Link
Question Link
How can I see the Late Start date for tasks?
How can I see the Late Start date for tasks?
Question Link
Question Link
Why should I use the Late Start and Late Finish fields?
Why should I use the Late Start and Late Finish fields?
Question Link
Question Link
How is the Late Start and Late Finish fields calculated?
How is the Late Start and Late Finish fields calculated?
Question Link
Question Link
Answer
When you first create a task, its late finish date is the same as the project finish date, and its late start date is calculated as the project finish date minus the task duration. As you link the task to predecessors and successors and apply any other constraints, application calculates the late start date as the last possible date this task could be started if all predecessor and successor tasks also start and finish on their late start and late finish dates.
How can I see the Early Finish date for tasks?
How can I see the Early Finish date for tasks?
Question Link
Question Link
How can I see the Early Start for tasks?
How can I see the Early Start for tasks?
Question Link
Question Link
What does the “Early Start and Early Finish fields calculation” do?
What does the “Early Start and Early Finish fields calculation” do?
Question Link
Question Link
Answer
When you first create a task, its early start and early finish dates are the same as the scheduled start and finish dates. As you link the task to predecessor and successor tasks and apply any date constraints, the early start and early finish dates are calculated as the earliest possible dates this task could start and finish if all predecessors and successors also start and finish on their respective early start and early finish dates. If there is a leveling delay on the task, this delay is also figured into the early start and finish dates. These calculations are based on a fixed duration.
How can I see the Cost Assignment on tasks?
How can I see the Cost Assignment on tasks?
Question Link
Question Link
How are Rate-based and Per-use costs applied to Work Resources and Material Resources?
How are Rate-based and Per-use costs applied to Work Resources and Material Resources?
Question Link
Question Link
Answer
The Rate-based cost as well as the Per-use cost operate in different ways, depending upon whether the resource is a work resource (a person, rental equipment etc.) or a material resource.The Standard Rate cost is Applied per hour for Work Resources and per unit assignment for Material Cost.The Per Use cost, for Material Resources applied once per assignment and for Work Resources depends on the assignment units used.A resource can have both a rate-based cost and a per-use cost set up
What is Rate-based cost?
What is Rate-based cost?
Question Link
Question Link
What do “Cost” represent in Project Plan 365?
What do “Cost” represent in Project Plan 365?
Question Link
Question Link
What does the “Calculation Duration, Start and Finish” functionality do?
What does the “Calculation Duration, Start and Finish” functionality do?
Question Link
Question Link
Answer
The “Calculation Duration, Start and Finish”, as the names describes, calculates the start and finish dates of tasks considering factors like constraints, linked tasks or other. For optimal scheduling flexibility, it's recommended that you allow application to calculate the start and finish dates for tasks based on the durations and task dependencies you enter. If you have unavoidable constraints, such as an event date, you can set a specific start or finish date for a task.
What information does the Variance table provide?
What information does the Variance table provide?
Question Link
Question Link
How can I compare the baseline and the scheduled information?
How can I compare the baseline and the scheduled information?
Question Link
Question Link
How can I change a summary task duration?
How can I change a summary task duration?
Question Link
Question Link
Where can I change the “Advanced Options” for my project?
Where can I change the “Advanced Options” for my project?
Question Link
Question Link