FAQ Project Plan 365

Browse by Category

Why am I not able to set the task type for a task?
Question Link
Answer
If the task type box is grayed out it means the task you have selected is a manual tasks . Task types apply only to automatically-scheduled tasks.
What role do task types have?
Question Link
Answer
Task types help to determine how duration, work and units will behave as Project Plan 365 schedules your project.
What happens when editing the units of a fixed units task?
Question Link
Answer
If you edit the units of a fixed units tasks, the duration will be recalculated.
What happens when editing the units of a fixed work task?
Question Link
Answer
If you edit the units of a fixed work task, the duration will be recalculated.
What happens when editing the units of a fixed duration task?
Question Link
Answer
If you edit the units of a fixed duration task, work will be recalculated.
What happens if I edit the duration of a fixed units task?
Question Link
Answer
If you edit the duration of a fixed units task, work will be recalculated.
What happens if I edit the duration of a fixed duration task?
Question Link
Answer
If you edit the duration of a fixed duration task, work will be recalculated.
What happens if I edit the work amount of a fixed units task?
Question Link
Answer
If you modify the work amount of a fixed units task, the duration will be recalculated.
What happens if I edit the work amount of a fixed work task?
Question Link
Answer
If you modify the work amount of a fixed work task, the duration will be recalculated.
What happens if I edit the work amount of a fixed duration task?
Question Link
Answer
If you modify the work amount of a fixed duration task, the units will be recalculated.
What is the difference between task types and task constraints?
Question Link
Answer
If you want to impose restrictions on the way the application calculates the start and finish dates, task constraints do the job rather than task types.
Why am I not able to change the task type of a summary task?
Question Link
Answer
Summary tasks are always fixed-duration types because a summary task's start and finish dates are determined by its subtasks.
How can I make all tasks manually in my new project?
Question Link
Answer
To make tasks scheduled manually click on File - Options - Schedule - New tasks created - Manually scheduled.
Can tasks be anything else but manually or automatically scheduled?
Question Link
Answer
Tasks can only be manually scheduled or automatically scheduled. Remember that manually scheduled tasks are not calculated by Planner.
When should I use manual tasks?
Question Link
Answer
Manual tasks should be used when you want to explicitly set a task's start and finish dates and not allow it to be changed automatically by the scheduler.
How to change a task from manual to auto?
Question Link
Answer
Double click on the task and go to Task Information, then check in the Schedule Mode the Auto Scheduled option.
Why do some of my tasks have the finish and start dates blank?
Question Link
Answer
Go to Format menu and click on Insert Column. Select in the Field Name - Task Mode. If you already have the task mode column skip the previous step. If the Task mode is manual change it to Auto. When tasks are Automatically scheduled, the Planner calculates the Start, Finish and Duration values.
Why is my manual task set to Fixed Duration?
Question Link
Answer
The task type for manual tasks is set to Fixed Duration to make them unchangeable for the Planner.
How to change the bar color for manual tasks?
Question Link
Answer
To change the bar color go to Format - Bar styles. Under the Name tab look for Manual Task and click on its Appearance field. Select the color you wish and press ok.
Is it possible to delete multiple tasks?
Question Link
Answer
You can delete multiple tasks by selecting multiple consecutive rows using either CTRL or SHIFT keys on you keyboard and then click on Delete option from the Task menu, or press on Delete key or use the Delete Task option from the contextual menu to delete multiple tasks at a time. The IDs of the remaining tasks will be automatically renumbered.​
Is it possible to insert more than one task at a time?
Question Link
Answer
​To insert multiple tasks, select multiple consecutive rows using either CTRL or SHIFT keys on your keyboard and then click on Insert option from the Task menu, or press on Insert key or use the New Task option from the contextual menu to insert multiple tasks at a time. These tasks will be positioned above the selected rows in the tasks list. The number of newly inserted tasks will be equal to the number of selected rows.​
Is it possible to insert a task between two tasks?
Question Link
Answer
To insert a task between existing tasks, select the row below where you want a new task to appear. On the Task tab, click the top part of the Insert button. A new task will be inserted having the title "New Task" and duration "1 day?​".
When should I create a recurring task?
Question Link
Answer
​Recurring tasks should be created when a task repeats at set intervals. If it does not repeat at set intervals, enter it as a regular task every time it occurs.
How can I move a task? It keeps the start date and duration as priority, rather then logic links I am giving with predecessors.
Question Link
Answer
​If a task has any actuals applied, such as an actual start date or a percentage of work completed, the task can't be rescheduled any earlier than the date when the task actually began. If no progress is entered and the task has an inflexible constraint, the constraint can take precedence over task dependencies. Please remove % complete values then try again to change predecessors value.
What role do Constraints have?
Question Link
Answer
Constraints allow you to control the start or finish date of an automatically-scheduled task.
Contact
Chat