How to insert the Leveling Delay column?
Question Link
Answer
To insert the Leveling Delay column, right click on the column before which you want to insert it, and from the contextual menu choose the “Insert column…” option. Select “Leveling Delay” for the “Filed name” and click the “OK” button.
When should I use the Leveling Delay field?
Question Link
Answer
Add the Leveling Delay field to a task view if you want to examine the delays to tasks caused by resource leveling.
How do I silently install Project Viewer for Mac?
Question Link
Answer

To silently install Project Viewer for Mac, follow the steps:

  1. Locate the installable file (ProjectViewer_365_Mac_v.pkg). 
  2. Open the Terminal window. 
  3. Locate the directory where you saved the installable file.
  4. Use the command sudo installer -pkg "ProjectViewer_365_Mac_v.pkg" -target / .
What are the available Erix menu options?
Question Link
Answer
The available Erix menu options are: “Help me with app functionalities”, “Show my project info”, “Help me with purchasing” and “Want to report a problem”.
What questions can Erix answer?
Question Link
Answer
Erix answers to questions regarding project planning, app functionalities or purchasing the app that usually start with “What is…”, “How do I…” or “Show me…”.We recommend using the same format for a better experience and for an easier learning process for Erix.
Can you send invoice after purchase?
Question Link
Answer
We automatically send to you the invoice attached to the confirmation order email. We send the confirmation order email on the email address you used when you placed the order.  You can also download the invoice from Project Plan 365 Portal by going to “Billing” tab – “Your Orders” section and click the “Invoice” action associated with the order you are interested in. Note that only Admins can access the “Billing” tab.
Where can I find all my previous orders?
Question Link
Answer
To see all your previous orders, please go to Project Plan 365 Portal – “Billing” tab and in the “Your Orders” section you will find all your previous orders. Note that only Admins can access the “Billing” tab.

Question Link
Answer
We are sorry but at this point you cannot costumize formulas.

Question Link
Answer
To move multiple tasks through you project plan you can select all the tasks you want to move, right-click on any selected ID number, click "Cut" then select the row over which you want to place the tasks , righ-click on the ID number and click "Paste".

Question Link
Answer
To export a view to PDF just switch to the view you want to export and go to File menu - Export - Export to PDF.

Question Link
Answer
In order to see the %Work Complete for a specific month, first go to Format menu - Insert, select the %Work Complete column an click OK. Then go to Project menu - Autofilter. Click on the autofilter arrow next to the column heading of the Start column and check only the month you want. The autofilter arrow and the column name will turn in blue.
Can I link other project?
Question Link
Answer
We are sorry but, at this point, you can not link two different projects, but you can create a Master project that contains all the subprojects you need. To do so you have to go to Project menu - Subprojects and select a project from Drive 365 or your Device.
How I can manage a dependency?
Question Link
Answer
You can manage the Task Dependency between two tasks in 2 ways:
1. From the Task Information Dialog, select a task, from the Task Menu click on Task Information, go to Predecessors tab, add a predecessor, select the Dependency Type and the Lag time if needed.2. In Gantt Chart double-click on the linking arrow between two tasks and from the Task Dependency dialog, select a Dependency Type and Lag time if needed.
What is the Critical Path Method?
Question Link
Answer

The Critical Path methodology identifies the paths of tasks most likely to impact the project completion date. This technique is used to help project managers to determine the shortest possible project duration and the level of flexibility that exists in the project. The critical path method calculates the early dates (Early Start and Early Finish), late dates (Late Start and Late Finish) and total slack.

Can you show me a Gantt Chart demo?
Question Link
Answer

You can read more about the Gantt Chart View in our Gantt Chart Online Article or in our All About Gantt Chart page, which also includes a video.

Is there a training course I can do offline?
Question Link
Answer

We are sorry but at the moment we only offer Online Training Courses and these can be found in our Online Training.

How do I see dependencies?
Question Link
Answer
In order to see the task dependencies you need to insert the Predeccessors Column by going to the Format menu - Insert Column, select the Predeccessors field from the "Field Name" box and then click OK in order for the changes to take effect.
How can I cancel my Business subscription from Microsoft Store?
Question Link
Answer
To cancel the Business Subscription, please go to "Help" menu - "Subscriptions" tab and click the "Cancel Subscriptions" button. Then, follow the instructions from Microsoft Store. We have no access to your account and cannot reach them on your behalf.
How can I cancel my Standard subscription from Microsoft Store?
Question Link
Answer
To cancel the Standard Subscription, please go to "Help" menu - "Subscriptions" tab and click the "Cancel Subscriptions" button. Then, follow the instructions from Microsoft Store. We have no access to your account and cannot reach them on your behalf.
How can I keep the outline structure when importing an excel file?
Question Link
Answer
In order to keep the outline structure, you can insert the column “Outline Level” into your project and then export it to Excel. After that, when importing it, the project structure will be the same as the one before exporting the project.
Why doesn't a milestone has a duration of 0 days?
Question Link
Answer
The milestones can also have a duration rather than 0 days and can be marked as milestones by selecting the tasks and going to the Task Information dialog – Advanced tab and checking the “Mark task as milestone” checkbox. Only if you do not need to allocate time for your Milestone you can set the tasks Duration to 0.
Does Project Plan 365 have Macros compatibility?
Question Link
Answer
We are sorry but there’s no compatibility between the MACROS of MS-Project and our application and we don’t run macros.
How can I import a PDF file?
Question Link
Answer
We are sorry but the Import from PDF functionality isn't available in our application at the moment.
How do I list the task types in a schedule?
Question Link
Answer
In order to see the task types, you need to insert the "Type" column. In order to do that, go to the Format menu, select the "Insert Column" option, from "Field Name" select "Type" and press "OK".
How do I show the Calendar type information in Gantt Chart?
Question Link
Answer
To add the Calendar information to Gantt bars, apply the Gantt Chart View – make sure you are not selecting any particular task or bar – on the Format menu, click Bar Styles- select the type of Gantt bar – click Text tab – select "Task Calendar" – click OK.