FAQ Project Plan 365
Browse by Category
What does the “Sign Up” functionality do?
What does the “Sign Up” functionality do?
Question Link
Question Link
What is the difference between Sign In and Sign Up with a third-party login?
What is the difference between Sign In and Sign Up with a third-party login?
Question Link
Question Link
Any project can be shared with other team members?
Any project can be shared with other team members?
Question Link
Question Link
Can I only share the file after I have bought the app?
Can I only share the file after I have bought the app?
Question Link
Question Link
Why do I need to set the password for my account?
Why do I need to set the password for my account?
Question Link
Question Link
What does the “Set Password” functionality do?
What does the “Set Password” functionality do?
Question Link
Question Link
What does the “Restore Subscription” functionality do?
What does the “Restore Subscription” functionality do?
Question Link
Question Link
On what platforms can I import team members from Resource Sheet view?
On what platforms can I import team members from Resource Sheet view?
Question Link
Question Link
How do I distinguish if a resource is already a team member or not?
How do I distinguish if a resource is already a team member or not?
Question Link
Question Link
How do I group resources in Resource Sheet view?
How do I group resources in Resource Sheet view?
Question Link
Question Link
How do I sort the resources in Resource Sheet view?
How do I sort the resources in Resource Sheet view?
Question Link
Question Link
How do I apply a filter in Resource Sheet view?
How do I apply a filter in Resource Sheet view?
Question Link
Question Link
Answer
In Resource Sheet view, you can use any of the resource filters to display only the information you want to see. When you select a filter, the Resource Sheet view displays the information as defined by that filter's criteria. The default filter is the All Resources filter. To apply a filter, go to menu Project - Filter.
How do I apply a different table in Resource Sheet view?
How do I apply a different table in Resource Sheet view?
Question Link
Question Link
Answer
The Resource Sheet view displays categories of information about the resources, arranged in tables. The default table for the Resource Sheet view is the Entry table, but you can select any of the resource tables to display information about the project's resources by going to menu Project - Tables.
How do I customize or format the Resource Sheet view?
How do I customize or format the Resource Sheet view?
Question Link
Question Link
Answer
To make the Resource Sheet view fit your needs exactly, you can customize it. To customize the Resource Sheet view, you can:
1. Change the information that is displayed.
2. Change the columns order
3. Format individual information to pay attention to it. For example, you can apply bold formatting to a higher-than-expected cost and assign a different font to an overallocated resource.
4. Format a category information to distinguish that type of information. For example, you can format all overallocated resources as italic text and increase the size of all column headings.
5. Create a combination view for the Resource Sheet view to display additional information about the resources in the Resource Sheet view or about the tasks to which those resources are assigned.
1. Change the information that is displayed.
2. Change the columns order
3. Format individual information to pay attention to it. For example, you can apply bold formatting to a higher-than-expected cost and assign a different font to an overallocated resource.
4. Format a category information to distinguish that type of information. For example, you can format all overallocated resources as italic text and increase the size of all column headings.
5. Create a combination view for the Resource Sheet view to display additional information about the resources in the Resource Sheet view or about the tasks to which those resources are assigned.
How do I use the Resource Sheet View?
How do I use the Resource Sheet View?
Question Link
Question Link
What kind of resources can I add in Resource Sheet view?
What kind of resources can I add in Resource Sheet view?
Question Link
Question Link
What is the Resource Sheet view?
What is the Resource Sheet view?
Question Link
Question Link
What does the “Renew Standard Subscription” functionality do?
What does the “Renew Standard Subscription” functionality do?
Question Link
Question Link
Can I renew a smaller number of subscriptions?
Can I renew a smaller number of subscriptions?
Question Link
Question Link
What does the “Renew Business Subscription” functionality do?
What does the “Renew Business Subscription” functionality do?
Question Link
Question Link
What does the “Registration” functionality do?
What does the “Registration” functionality do?
Question Link
Question Link
On what platforms can I import team members from Gantt Chart view?
On what platforms can I import team members from Gantt Chart view?
Question Link
Question Link
How do I zoom in or zoom out in Gantt Chart view?
How do I zoom in or zoom out in Gantt Chart view?
Question Link
Question Link
Answer
The timeline units for the right portion of the Gantt Chart view are displayed at the top of the chart. By default, displays two units of time. You can adjust these time units to display up to three units of time, and you can change it so that different time units are displayed. For example, you can zoom out to a bigger picture of your project's tasks by displaying Years and Months, or you can zoom in to see the exact start and finish dates for your project's tasks by changing the timescale to Weeks and Days. In order to Zoom In/Out, go to menu Project - Zoom.
How do I sort the tasks in Gantt Chart view?
How do I sort the tasks in Gantt Chart view?
Question Link
Question Link
How do I group tasks in Gantt Chart view?
How do I group tasks in Gantt Chart view?
Question Link
Question Link