FAQ Project Plan 365

Browse by Category

How do I open the Project Information dialog?
Question Link
Answer
In order to open Project Information dialog, go on Project menu – Project Information.
How do I revert to original sort order?
Question Link
Answer
In order to revert to original sort order, go to menu Project-Sort-Sort By and click on Reset button.
What does the "Work Incomplete" filter do?
Question Link
Answer
The "Work Incomplete" filter allows seeing all resources with scheduled work less than the baseline work.
What does the "Work Complete" filter do?
Question Link
Answer
The "Work Complete" filter allows seeing resources that have completed all of their assigned tasks.
What does the "Resource Work" filter do?
Question Link
Answer
The "Resource Work" filter allows seeing all the resources of type work.
What does the "Resource Material" filter do?
Question Link
Answer
The "Resource Material" filter allows seeing all the resources of type material.
What does the "Resource Cost" filter do?
Question Link
Answer
The "Resource Cost" filter allows seeing all the resources of type cost.
What does the "Overallocated Resources" filter do?
Question Link
Answer
The "Overallocated Resources" filter allows seeing all resources with a scheduled cost greater than the baseline cost.
What does the "Unstarted Assignments" filter do?
Question Link
Answer
The "Unstarted Assignments" filter allows seeing all assignments that haven't yet started.
What does the "Slipping Assignments" filter do?
Question Link
Answer
The "Slipping Assignments" filter allows seeing all assignments that have slipped from their original baseline plan.
What does the "In Progress Assignments" filter do?
Question Link
Answer
The "In Progress Assignments" filter allows seeing the assignments that have been started but not yet completed.
What does the "Resource Range..." filter do?
Question Link
Answer
The "Resource Range..." filter allows seeing ll resources that have ID numbers within the specified range.
What does the "Group" filter do?
Question Link
Answer
The "Group" filter allows seeing all resources belonging to a specified group.
What does the "All Resources" filter do?
Question Link
Answer
The "All Resources" filter allows seeing all resources, regardless of their particularities.
What filters can I apply in Resource views?
Question Link
Answer
In Resource views you can apply the following filters: All Resources, Group, Overallocated Resources, Resource Cost, Resource Material, Resource Range, Resource Work, Unstarted Assignments, Work Complete, Work Incomplete.
Can I import standard tables across different languages? 
Question Link
Answer
In Project Plan 365 app you can import standard tables across different languages.
What are the Project Statistics?
Question Link
Answer

Project Statistics are a set of crucial information gathered for an overall view of the project. With this functionality, you can easily review scheduled and actual start and finish dates, durations, work, and costs.

What is Committed Portfolio Selection Decision (Schedule) field?
Question Link
Answer
The Committed Portfolio Selection Decision (Schedule) field shows the commitment date of a Portfolio Selection Scenario as determined during schedule constraint analysis.
Where can I access all tables?
Question Link
Answer
To learn how to access all tables please read this article: https://www.projectplan365.com/articles/tables/.
What role have the columns named Number1 to Number20?
Question Link
Answer
The columns "Number1"…"Number20" are designed for customized use. The name shows the data type it accepts.
What means an outline symbol presenting a plus sign?
Question Link
Answer
An outline symbol presenting a plus sign indicates a summary task with its subtasks hidden.
What means an outline symbol presenting a minus sign?
Question Link
Answer
An outline symbol presenting a minus sign indicates a summary task with its subtasks showing.
What is Workflow State field?
Question Link
Answer
The Workflow State field indicates a selected proposal or project's current workflow state—for example, Waiting For Approval or Completed. This field is a component of the Microsoft Project Server workflow framework.
What is Workflow Stage Name field?
Question Link
Answer
The Workflow Stage Name field specifies the current workflow stage name for a selected project. A stage represents a single step within a project life cycle, and one or more stages can make up a workflow phase. This field is a component of the Microsoft Project Server workflow framework.
What is Workflow Stage Info field?
Question Link
Answer
The Workflow Stage Info field describes the current workflow stage for a selected project. A stage represents a single step within a project life cycle, and one or more stages can make up a workflow phase. This field is a component of the Microsoft Project Server workflow framework.
Contact
Chat