FAQ Project Plan 365

Browse by Category

How can I update Actual Start and Finish Dates of a task using the Update Tasks functionality?
Question Link
Answer
To update the Actual Start and Finish Dates of a task, go to menu Tasks – Mark on Track – Update Tasks. In the Update Tasks dialog, from the Actual section, set the desired actual Start and Finish dates by selecting them from the date picker then click OK for the changes to be applied.
What is the Actual Start/Finish dates field?
Question Link
Answer
The Actual Start field shows the date and time that a task or an assignment actually began, based on progress information that you entered. The Actual Finish field shows the date and time when a task or assignment was completed.
What is the Remaining Duration field?
Question Link
Answer
The Remaining Duration field shows the time that is required to complete the unfinished part of a task.
What is the Actual Duration field?
Question Link
Answer
The Actual Duration field shows the span of actual working time for a task to this point, based on the scheduled duration and current remaining work or percent complete.
Where can I find the Update Tasks functionality?
Question Link
Answer
To find the Update Tasks functionality go to menu Task – Mark on Track – Update Tasks button.
What is the Update Tasks functionality?
Question Link
Answer
The Update Tasks functionality allows you to quickly update information like: %Complete, Actual Duration, Remaining Duration, Actual Start/Finish dates for all selected tasks.
How can I set the Assignment Owner?
Question Link
Answer
We are sorry, but The Assignment Owner field is not editable in our application at this point.
Why is the Zoom option greyed out in the Task Sheet view?
Question Link
Answer
We are sorry, but you cannot Zoom In/Zoom Out in the Task Sheet view at this point.
What information do I need about master project and subprojects files?
Question Link
Answer

1. When you insert a subproject, a small specific icon distinguishes it from summary tasks that are part of the master project.

2. In the master project, subprojects appear as summary tasks that you can easily arrange in an outline.

3. Click the collapsed sign next to a subproject to expand that subproject's tasks for viewing.

4. Each subproject represents a different phase or another functional group in the main project.

5. When you insert a subproject into the master project, the two projects are linked and you can view all the information in the subproject from the master project.

6. If you want to edit a subproject, it will be opened in a new window that allows you to edit the subproject and save it. The changes made to the subproject will be automatically updated in the master project.

7. When you update a subproject from the master project, it is updated in its source file as well.

8. If you just must combine files to create a report or print a view of combined-project information, you can also consolidate them temporarily in a view.

Note: On Web and iOS platforms, if you want to edit a subproject, the app will ask you to open the subproject separately to make the desired changes.

How do I know if another team member made changes to a subproject?
Question Link
Answer

When another team member makes changes to a subproject that is part of a master project, an icon appears in the Indicator field for the modified subproject. Click on the refresh icon and a message will appear asking if you want to update the master project.

How do I edit Actual Work field?
Question Link
Answer

To edit the Actual Work field, first insert it by going to menu Format – Insert Column, from the Field Name dropdown list select Actual Work and click OK then type in the desired value.

What does the “Help” button inside the “Update Project” dialog do?
Question Link
Answer
The “Help” button inside the “Update Project” dialog redirects you to the “Update Project” article in our Online Help page.
How can I reschedule only the remaining work of tasks that are in progress?
Question Link
Answer
To reschedule only the remaining work of tasks that are in progress, go to menu Project – Update Project, check “Reschedule uncompleted work to start after” option then check the “Split in-progress tasks” option and click OK. The tasks that are in progress will be split and the remaining work will be rescheduled based on selected date.Note: If you don't specify a date, Project Plan 365 uses the current or status date.
Can I reschedule uncompleted work to start after a different date than the current or Status Date?
Question Link
Answer
If you don't specify a date, Project Plan 365 uses the current or status date. The unfinished work can be rescheduled to start after a different date by going to menu Project – Update Project and from the “Reschedule uncompleted work to start after:” section select a different date from the date picker. Set the desired options and click OK.
Can I update my project to a different date than the current or Status Date?
Question Link
Answer
If you don't specify a date, Project Plan 365 uses the current or status date. The project can be updated based on a different date by going to menu Project – Update Project and from the “Update work as complete through:” section select a different date from the date picker. Set the desired options and click OK.
Can I reschedule uncompleted work only for selected tasks in a project?
Question Link
Answer
You can reschedule uncompleted work only for Selected tasks by going to menu Project – Update Project, select the “Reschedule uncompleted work to start after” and select a date from the date picker. From the “For:” section check the “Selected tasks” checkbox and click OK.Note: If you don't specify a date, Project Plan 365 uses the current or status date.
Can I update only selected tasks from a project?
Question Link
Answer
You can update only Selected tasks from a project by going to menu Project – Update Project, select the “Set 0% - 100% complete” or “Set 0% or 100% complete only” option under the “Update work as complete through:” and select a date from the date picker. From the “For:” section check the “Selected tasks” checkbox and click OK.Note: If you don't specify a date, Project Plan 365 uses the current or status date.
How can I reschedule uncompleted work in a project?
Question Link
Answer
To reschedule uncompleted work in your project, go to menu Project – Update Project, check “Reschedule uncompleted work to start after” option, select a date from the date picker then click OK. All tasks will be updated and uncompleted / unstated work will be rescheduled.Note: If you don't specify a date, Project Plan 365 uses the current or status date.
How can I update the entire project with 0% or 100% complete only?
Question Link
Answer
To update your project with 0% or 100% complete only, go to menu Project – Update Project, make sure the “Set 0% or 100% complete only” option is checked under the “Update work as complete through:” section, select a date from the date picker and click OK.Note: If you don't specify a date, Project Plan 365 uses the current or status date.
How can I update the entire project with any %Complete?
Question Link
Answer
To update the project with any %Complete, go to menu Project – Update Project, make sure the “Set 0% - 100% complete” option is checked under the “Update work as complete through:” section, select a date from the date picker and click OK.Note: If you don't specify a date, Project Plan 365 uses the current or status date.
Where can I find the Update Project functionality?
Question Link
Answer
To find the Update Project functionality go to menu Project – Update Project button.
What is the Update Project functionality?
Question Link
Answer
The Update Project functionality allow you to quickly update your project's tasks to 100% complete or the scheduled percent complete.
How do I open a project from Project Plan 365 Portal?
Question Link
Answer
To open a project from Project Plan 365 Portal using our application, go to our Online Portal, then Sign In with your email and password.Go to Projects page and click on a project name. A dialog will appear asking you to make sure you have the latest app version installed on your device by clicking the Download Project Plan 365 app.If you already have the latest version, click on the Open in Project Plan 365 button. The browser will request to allow Project Plan 365 Portal to open the app. Click Open Project Plan 365 and the project will be opened in the application.Note: In the browser request, check the “Always allow www.projectplan365.com to open links of this type in the associated app” checkbox so the request won’t appear each time.
How do I start a new project from Project Plan 365 Portal?
Question Link
Answer

To start a new project from Project Plan 365 Portal using our application, go to our Online Portal, then Sign In with your email and password. If you don’t have an account, you can create one or you can Sign In with a third-party login. Go to Projects page and click on the Create new project button. A dialog will appear asking you to make sure you have the latest app version installed on your device by clicking the Download Project Plan 365 app.If you already have the latest version, click on the Create New Project button. The browser will request to allow Project Plan 365 Portal to open the app. Click Open Project Plan 365 and the application with a new project will open.Note: In the browser request, check the “Always allow www.projectplan365.com to open links of this type in the associated app” checkbox so the request won’t appear each time.

I renewed my Standard Editor subscription for iProject Viewer from App Store. How can I update my Project 365 account info?
Question Link
Answer
If you have renewed your Standard Editor subscription and the data has not been updated into the Project 365 application please follow the steps below:  
  1. Make sure you downloaded and installed our latest application from App Store. 
  2. Open iProject Viewer application. 
  3. Go to menu Help - Register – Manage Apple Store Subscriptions. 
  4. Press on RestoreStandard EditorSubscription. 
  5. Wait for the confirmation message. 
  6. Sign In with your Project 365 email and password inside the application in order to transfer the subscription information from App Store to your Project 365 account.  
Contact
Chat