How do I add a predecessor?
Question Link
Answer
To add predecessors to tasks, go to Gantt Chart view and in Predecessors field insert the Task IDs.
How do I change the constraint to a task?
Question Link
Answer
To change the constraint to a task, select the given task and click on Task - Task Information - Advanced. Constraint information is in the Constraint type and Constraint date boxes. Change the Constraint Type and click on the Ok button.
How do I change all the constraint types to as soon as possible?
Question Link
Answer
We are sorry, but at this point, you cannot change all the constraint types at once.
What language does Erix know?
Question Link
Answer
English is Erix's native language.
How do I remove Erix chat?
Question Link
Answer
We are sorry, but at this point, the Erix Chat cannot be removed.
How can I change the duration from days to weeks?
Question Link
Answer
To change the duration unit, go to menu File - Options - Advanced tab and on "Duration is entered in" field select the desired unit and press on the OK button.
How do I put out a current date line?
Question Link
Answer
In order to apply a line for the current date, go to Gantt Chart view and go to menu Format - Gridlines and select the Current Date.  Set the color and the line type and click on the OK button.
Can I use the Dashboard functionality on the web application? 
Question Link
Answer
On the web application, you can only open an existing Dashboard file, but you cannot create a dashboard file.
How Set Baseline works in a MPP file?
Question Link
Answer

To set baseline start/duration/finish first set them in the Entry table and then use set baseline option under menu Project - Set Baseline.

How do I create a master project file?
Question Link
Answer

To create a master project with subprojects first you need to make sure that you purchased the Business Subscription from our website.
Go to menu Project - Subproject -  Drive 365 or Computer. Select the desired mpp file and click Open.

Why is the Late Start Date field different to the Start Date field?


Question Link
Answer

The Late Start Date field represents the latest date an activity can start without affecting the planned project finish date. The Start Date field shows the date when a task is scheduled to begin.

How to spell check the full project at the same time?
Question Link
Answer
We are sorry, but you cannot spell-check the full project at the same time. You can use the spell-check feature for each task.
How do I chek the project cost?
Question Link
Answer
In order to check the project cost, please go to menu Project - Project Information and click on the Statistics button.
How to change the early start date?
Question Link
Answer
We are sorry, but the Early Start Date field is read-only at this point.
How do I change the paper size in PDF format?
Question Link
Answer
To change the paper size when you want to print or to export to PDF, go to menu File - Print - Page Setup and select another Paper Size.
How do I see a progress chart?
Question Link
Answer
You can see a progress chart creating a custom report or a visual report by going to menu Report - Custom Reports - New.
Does the question mark in the Duration box have any meaning?
Question Link
Answer

The default duration for new tasks has a question mark (1d?). The question mark indicates that the duration is an estimate. Add a question mark to any duration estimate. Remove the question mark to indicate a committed duration.

How do I access the customer service?
Question Link
Answer
Please submit a ticket to our Support Team:https://www.projectplan365.com/feedback/index.
Why the weekend days are black now?
Question Link
Answer
In order to change the color for weekend days or non-working days, please double click on the Timescale bar in Gantt Chart view. Go to Non-working time tab and on Color section select a new color and press Ok.
I want to do page set up but they are telling me the from date must be before to date.
Question Link
Answer
Please make sure that the FROM date is before the TO date.
Can I experience collaborative mode during the trial period?
Question Link
Answer
In order to evaluate the real-time collaboration feature, please start a 30 days Business Trial on our Project Plan 365 Portal: https://www.projectplan365.com/ups/Account/SignUp. Then, Sign In with your email and password inside the Project Plan 365 app and open a file previously saved in My Projects - Drive 365 cloud service. Then, enable the Collaboration by going to menu Team – Collaborate.
Where to enter the license key?
Question Link
Answer
To enter the license key, go to menu Help - Register. Insert the license key and click on the Register button. Please note that if you purchased the Standard or Business Subscription for Project Plan 365 app, you don't need a license key, just Sign In with your email and password inside Project Plan 365 app.
How can I edit the task?
Question Link
Answer
You can edit mpp files using our editor tool Project Plan 365: https://www.projectplan365.com/download/.
How to flag a task?
Question Link
Answer
To flag a task you can insert a custom field of type Flag. Go to menu Format - Insert Column. Select a field from Flag1-20 insert a Title and click on the Ok button.
How to change the marked status to yes?
Question Link
Answer
We are sorry, but the Marked task field is not editable at this point. As a workaround, you can insert a column of type Flag in your project.