FAQ Project Plan 365

Browse by Category

How many projects can I add in a Scheduled Report?
Question Link
Answer
In a Scheduled Report you can add only 10 projects. If you want to select more than 10 projects, the following message will be displayed: “Limit reached (10 items max)”.
What does the Scheduled Reports functionality do?
Question Link
Answer
The Scheduled Reports functionality allows you to schedule and customize Project Status reports.
I would like to add week numbers to the timescale.
Question Link
Answer
To customize the Timescale, go on Gantt Chart (or other view with a timescale), then open Timescale dialog by double clicking on it or by going to the Format Menu – Timescale and make the desired changes in Top Tier, Middle Tier, or Bottom Tier tab.In the Label field you can select the format of the Weeks: Week 1, Week 2, Week 3…/W1, W2, W3…/1, 2, 3… and more.
How do I enter an elapsed duration for a task?
Question Link
Answer
We are sorry but at this point, entering elapsed duration for tasks is not possible in our application.
How can I keep the project structure when using the "Export to excel" functionality?
Question Link
Answer
We are sorry but keeping the project structure when exporting to Excel, is not possible at this moment in our application.

I am not able to find the "Link" button on my iPad application.


Question Link
Answer
We are sorry but at this moment the Link and Unlink buttons are not available in our iOS application.
How can I export the .mpp file in a different format?
Question Link
Answer
Our application allows you to export your .MPP files to ExcelPDF, Image, PowerPoint, XML, Dashbord and MPP.

How to Install the Project Plan 365 for iPad?


Question Link
Answer

In order to install Project Plan 365 for iPad, follow the steps below: 

1. Go to our Download page.

2. Select the iOS platform and click on the Download Project Plan 365 button. 

3. Use your Apple ID in App Store to download and install Project Plan 365 app to your iPad.

How do I apply the "Work Overbudget" filter?
Question Link
Answer

In order to apply the "Work Overbudget" filter, go to menu Project - Filter and select More Filters then select Work Overbudget and click on Apply button.

How do I apply the "Work Incomplete" filter?
Question Link
Answer

In order to apply the "Work Incomplete" filter, go to menu Project - Filter and select More Filters then select Work Incomplete and click on Apply button.

How do I apply the "Work Complete" filter?
Question Link
Answer

In order to apply the "Work Complete" filter, go to menu Project - Filter and select More Filters then select Work Complete and click on Apply button.

How do I apply the "Late/Overbudget Tasks Assigned To…" filter?
Question Link
Answer

In order to apply the "Late/Overbudget Tasks Assigned To…" filter, go to menu Project - Filter and select More Filters and then select Late/Overbudget Tasks Assigned To… and click on Apply button.

How do I apply the "Cost Overbudget" filter?
Question Link
Answer

In order to apply the "Cost Overbudget" filter, go to menu Project - Filter and select More Filters then select Cost Overbudget and click on Apply button.

How do I apply the "Cost Greater Than..." filter?
Question Link
Answer

In order to apply the "Cost Greater Than..." filter, go to menu Project - Filter and select More Filters then select Cost Greater Than... and click on Apply button.

How do I apply the "Using Resource in Date Range…" filter?
Question Link
Answer

In order to apply the "Using Resource in Date Range…" filter, go to menu Project - Filter and select More Filters then select Using Resource in Date Range… and click on Apply button.

How do I apply the "Tasks/Assignments with Overtime" filter?
Question Link
Answer

In order to apply the "Tasks/Assignments with Overtime" filter, go to menu Project - Filter and select More Filters then select Tasks/Assignments with Overtime and click on Apply button.

How do I apply the "Summary Task with Assigned Resources" filter?
Question Link
Answer

In order to apply the "Summary Task with Assigned Resources" filter, go to menu Project - Filter and select More Filters and then select Summary Task with Assigned Resources and click on Apply button.

How do I apply the "Resource Work" filter?
Question Link
Answer

In order to apply the "Resource Work" filter, go to menu Project - Filter and select More Filters then select Resource Work and click on Apply button.

How do I apply the "Resource Material" filter?
Question Link
Answer

In order to apply the "Resource Material" filter, go to menu Project - Filter and select More Filters then select Resource Material and click on Apply button.

How do I apply the "Resource Cost" filter?
Question Link
Answer

In order to apply the "Resource Cost" filter, go to menu Project - Filter and select More Filters then select Resource Cost and click on Apply button.

How do I apply the "Overallocated Tasks" filter?
Question Link
Answer

In order to apply the "Overallocated Tasks" filter, go to menu Project - Filter and select More Filters then select Overallocated Tasks and click on Apply button.

How do I apply the "Overallocated Resources" filter?
Question Link
Answer

In order to apply the "Overallocated Resources" filter, go to menu Project - Filter and select More Filters then select Overallocated Resources and click on Apply button.

How do I apply the "No Resource Assigned" filter?
Question Link
Answer

In order to apply the "No Resource Assigned" filter, go to menu Project - Filter and select More Filters then select No Resource Assigned and click on Apply button.

How do I apply the "Top Level Tasks" filter?
Question Link
Answer

In order to apply the "Top Level Tasks" filter, go to menu Project - Filter and select More Filters then select Top Level Tasks and click on Apply button.

How do I apply the "Tasks without Dates" filter?
Question Link
Answer

In order to apply the "Tasks without Dates" filter, go to menu Project - Filter and select More Filters then select Tasks without Dates and click on Apply button.

Contact
Chat