How do I change the Date Display Format for bars in Gantt Chart?
Question Link
Answer

To change the Date Display Format for bars in Gantt Chart, using the Gantt Chart view, go to menu Format – Layout and select a date format in the Date Format box then click on the OK button.

How do I change the appearance of link lines between Gantt bars?
Question Link
Answer

To change the appearance of link lines between Gantt Chart bars, using the Gantt Chart view, go to menu Format – Layout and select the desired type of link line, then click on the OK button.

What does the “Layout” functionality do?
Question Link
Answer

The “Layout” functionality allows the user to modify the Gantt Chart in several ways to make it easier to review. You can adjust the height of bars, the link design between bars, modify the date format of the bars, roll-up tasks so that a projection of the subtasks on Gantt Chart bar is displayed at the summary task.

How can I install the application on other device or platform?
Question Link
Answer

​If you purchased the subscription from our website, please download and install our latest application from this link: https://www.projectplan365.com/download/.

Then, Sign In with your email and password inside the application (look upper right corner for Sign In button).

Why are the options in the resource menu grayed out?
Question Link
Answer

If the resource tabs from the Resource menu are grayed out, you need to select the Resource Sheet View from the View menu and then go to the Resources menu.

When I assign a team member to my organization, will he/she receive an email?
Question Link
Answer

When you assign a team member to your business, if he/she has an account on our website, he/she will receive an email to join your Business. If the assigned team member doesn't have an account, the user receives a link inside the email to set the password for his new account.​​

I cannot see the Gantt Chart view.


Question Link
Answer

In order to use the Gantt Chart view, go to menu View - Gant Chart. Please know that the Gantt Chart view is the default view for the new projects.

I can't use the Free Viewer mode without the tool showing me the window to Start the Free Trial.
Question Link
Answer

When using Project Viewer 365 in free viewer mode, please make sure you are in Gantt Chart, Resource Sheet or Task Sheet view as only these 3 views are free.

How can I draw PERT chart?
Question Link
Answer
The PERT chart is called the Network Diagram in Project Plan 365 app. You can view the Network Diagram view by going to menu View - Network Diagram.
How can I take a full screenshot of the Gantt Chart?
Question Link
Answer
To take a full screenshot of the Gantt Chart view, you can export the entire view on one page. To achieve this,  go to menu File - Print. Click on the Page Setup button and a dialog will open and you will see that there is the Scaling option. Check the option Fit to 1 pages wide by 1 tall. Then, go to menu File-Export-Export to PDF.
How can I convert this file to MS Project 2013?
Question Link
Answer
The MPP files saved with Project Plan 365 are compatible with Microsoft Project 2010 and newer versions.
Do you have an early version of Project Plan 365?
Question Link
Answer
Our earliest version available on our website is the 2016 version that can be downloaded at https://www.projectplan365.com/articles/pp365downloadarchive/.
Do you have a new version of Project Plan 365?
Question Link
Answer
Our latest version can be found at https://www.projectplan365.com/download/.
Where is the task board?
Question Link
Answer
In order to see the Agile boards, please go to menu Project - Agile.
What is Task Mode field?
Question Link
Answer

The Task Mode field indicates whether a task is scheduled manually or automatically, which gives you the option of deciding how much control you want over task scheduling in a project. By default, tasks are set as automatically scheduled.

How can I fit to one page?
Question Link
Answer

To fit the entire project to one page, go to menu File - Print. Click on the Page Setup button and a dialog will open and you will see that there is the Scaling option. Check the option Fit to 1 pages wide by 1 tall.

How do I only include specific items in the legend?
Question Link
Answer
You can include only some specific items in the legend by going to Page Setup - Legend tab. Make the desired changes and click on the Ok button.
How do I build a WBS?
Question Link
Answer
To create a WBS, you need to Indent and Outdent tasks from menu Task - Indent/Outdent. In order to see the WBS, please insert the WBS column in Gantt Chart view.
How do I find when tasks were added?
Question Link
Answer
To see when the tasks were added you can insert the Created column in Gantt Chart view.
How do I see the successor?
Question Link
Answer
To see the successor for a task, insert the Successor field in Gantt Chart view. Go to menu Format - Insert Column. Select the Successors field and click on the Ok button.
How do I freeze column?
Question Link
Answer
We are sorry, but this feature is not available at this point.
How can I print in A1 format in the online version?
Question Link
Answer
We are sorry, but you cannot print in A1 format on our web application at this point.
How do I roll up to a total project % complete?
Question Link
Answer
To change the %complete for the entire project, please insert the Summary Project in your plan by going to menu File-Options-Advanced tab and check Show Project Summary Task. Then, in the Gantt Chart view, change the percent complete for the project summary task.
How do I save as MS Project 2007 format?
Question Link
Answer
We are sorry, but the MPP files saved with Project Plan 365 are compatible with Microsoft Project 2010 and newer versions.
How to make the next task start at end of the previous task?
Question Link
Answer
To make a task start when another task is finished, you need to establish a Finish to Start dependency in Predecessors column or in Task Information dialog under the Predecessors tab.