FAQs Scheduling
Browse by Category
FAQ › Category: How do I...? › Scheduling
How can I update the entire project with 0% or 100% complete only?
How can I update the entire project with 0% or 100% complete only?
Question Link
Question Link
Answer
To update your project with 0% or 100% complete only, go to menu Project – Update Project, make sure the “Set 0% or 100% complete only” option is checked under the “Update work as complete through:” section, select a date from the date picker and click OK.Note: If you don't specify a date, Project Plan 365 uses the current or status date.
How can I update the entire project with any %Complete?
How can I update the entire project with any %Complete?
Question Link
Question Link
Answer
To update the project with any %Complete, go to menu Project – Update Project, make sure the “Set 0% - 100% complete” option is checked under the “Update work as complete through:” section, select a date from the date picker and click OK.Note: If you don't specify a date, Project Plan 365 uses the current or status date.
Where can I find the Update Project functionality?
Where can I find the Update Project functionality?
Question Link
Question Link
What is the Update Project functionality?
What is the Update Project functionality?
Question Link
Question Link
Can I set the Deadline for the entire project?
On what platforms can I set Project Task Status Method?
On what platforms can I set Project Task Status Method?
Question Link
Question Link
Is the “Share” functionality also available in the Project Plan 365 for iPhone app?
Is the "Share" functionality also available in the Project Plan 365 for iPhone app?
Question Link
Question Link
Why isn’t the “Task Status Method” field available in my Options dialog?
Why isn’t the “Task Status Method” field available in my Options dialog?
Question Link
Question Link
Answer
If the Task Status Method field isn’t available in the Project Plan 365 application, please make sure you have the latest version of the application installed on your device: Download
What does the “Help” button inside the “Update Task Status Method” dialog do?
What does the “Help” button inside the “Update Task Status Method” dialog do?
Question Link
Question Link
What do the Project Status values represent?
What do the Project Status values represent?
Question Link
Question Link
Answer
The Project Status indicates the current status of your project: Complete, On Schedule, Late, Future, On Budget or Overbudget:
- Complete – If the project is 100% complete, then our application sets the Project Status to Complete.
- On Schedule – If percent complete is spread to at least the day before the status date, then the Project Status is On Schedule.
- Late – If percent complete does not reach midnight on the day before the status date, then the Project Status is Late.
- Future – If the Start Date of the project is greater than the Status Date, then the Project Status is set to Future.
- On Budget – If the project total cost is less or the same amount as the set project maximum cost, then the Project Status is set to On Budget.
- Overbudget – If the project total cost is over the set project maximum cost, then the Project Status is set to Overbudget.
Why does the task status not contain budget information?
Why does the task status not contain budget information?
Question Link
Question Link
How can I check if a task in on budget?
How can I check if a task in on budget?
Question Link
Question Link
How can I check if a task status is complete?
How can I check if a task status is complete?
Question Link
Question Link
How can I check if a task status is future?
How can I check if a task status is future?
Question Link
Question Link
How can I check if a task status is late?
How can I check if a task status is late?
Question Link
Question Link
How can I check if a task status is on schedule?
How can I check if a task status is on schedule?
Question Link
Question Link
Can I set the Task Status Method for all my organization projects?
Can I set the Task Status Method for all my organization projects?
Question Link
Question Link
Answer
To set the Task Status Method for all your organization projects, go to menu File – Account – Organization Information – Global Settings – Schedule Tab and from the Task Status Method field select the desired method. Learn more about Global Settings functionality.
Note: To have these settings applied to all your organization projects, make sure you create projects using the New blank project using Global Settings or New Blank Project Using Global Settings options from Home / New menu.
How can I see the status of all tasks in my project?
How can I see the status of all tasks in my project?
Question Link
Question Link
Answer
To see the status of all tasks in your project, in the Gantt Chart View or any other View with grids, add the Status column by going to menu Format– Insert Column, select Status and click OK.
Or you can apply the Status table by going to menu Project – Tables – More Tables, select the Status table and click Apply.
Or you can apply the Status table by going to menu Project – Tables – More Tables, select the Status table and click Apply.
How can I see the status of the entire project?
How can I see the status of the entire project?
Question Link
Question Link
Can I have different tasks with different Task Status Methods?
Can I have different tasks with different Task Status Methods?
Question Link
Question Link
How do I know if a task is late?
How do I know if a task is late?
Question Link
Question Link
How do I know if a task is over budget?
How do I know if a task is over budget?
Question Link
Question Link
How to add a Max Cost field in my project?
How to add a Max Cost field in my project?
Question Link
Question Link
Answer
To add the Max Cost field in your project, go to menu File – Options – Schedule tab and from the Task Status Method field select “Deadline and MaxCost”. When selecting this method, a new Max Cost field will appear. From this field, select the desired “Cost” custom column that will show the MaxCost for tasks, then click OK. Go to Gantt Chart View or any other View with grids, select a column and go to menu Format – Insert Column. Select the “Cost” custom column that has “MaxCost” in the name and click OK.
How can I update the Task Status Method?
How can I update the Task Status Method?
Question Link
Question Link
Answer
To Update the Task Status Method of your project you can either go to menu File – Options – Schedule Tab and change the methos from the Task Status Method field. Or, if you have the default Tasks Status Method set for your project and you edit the Deadline or Max Cost field in the menu Project - Project Information, a dialog will be displayed proposing to update the Task Status method from the default “% Complete and Status Date” to “Deadline and Max Cost” method and set Max Cost custom field.
What is the difference between the “%Complete and Status Date” and “Deadline and Max Cost” Task Status Methods?
What is the difference between the “%Complete and Status Date” and “Deadline and Max Cost” Task Status Methods?
Question Link
Question Link
Answer
The difference between the “%Complete and Status Date” and “Deadline and Max Cost” Task Status Methods is that the returned status of your project will depend on the entered %Complete and set Status Date for the first method and will depend on the set deadlines and entered maximum cost in for the second method.