What is the difference between Fixed Units and Fixed Duration?
Question Link
Answer

The difference between fixed units and fixed duration can be seen when modifying the units and work for a task. For Fixed units tasks, when revising units and work -duration is recalculated. For fixed duration tasks, when revising units - work is recalculated and when revising work-units are recalculated.

How do I change a task type ?
Question Link
Answer

To change a task type, double click on the task name in the Gantt Chart, then in the Task Information dialog, go to Advanced tab and in the Task Type group select Fixed Units, Fixed Work or Fixed Duration and then click OK.

What happens if I edit the duration of a fixed work task?
Question Link
Answer

If you edit the duration of a fixed work task, nothing happens. Changing scalar work after making an assignment on a task will no longer automatically alter the Assignment Units field.

I want to have the Task Mode information for all tasks in Gantt Chart.
Question Link
Answer

To see the Task Mode field, use Insert column option under Format menu and select in the Field Name: Task Mode.

You can insert and display this column in views like Gant Chart, Tracking Gant or Task Sheet view. 

Task Mode column displays an icon indicating whether a task, is a manually scheduled task, or an automatically scheduled task.

What is Lead time?
Question Link
Answer

Lead time is overlap between tasks that have a dependency.

For example, if a task can start when its predecessor is half finished, you can specify a finish-to-start dependency with a lead time for the successor task. You enter lead time as a negative value.

What is Lag time?
Question Link
Answer

Lag time is a delay between tasks that have a dependency. 

For example, if you need a two-day delay between the finish of one task and the start of another, you can establish a finish-to-start dependency and specify two days of lag time. You enter lag time as a positive value.

How can I make a manual task a milestone ?
Question Link
Answer

To make a manual task a milestone, double-click on the task. In the Task information - Advanced tab, check "Mark task as milestone" - click OK.

What is a task note?
Question Link
Answer

A task note is a written message associated with a task.

How do I insert a recurring task between existing tasks?
Question Link
Answer
To insert a recurring task between existing tasks, select the row below where you want a new recurring task to appear.Then select Insert - Recurring Task from Task tab.Fill in all info in recurring task dialog.The new recurring task will be inserted above the selected task.The task IDs are automatically renumbered after you insert a recurring task.
In what views is allowed to insert recurring tasks?
Question Link
Answer
Create recurring task is allowed only in Gantt Chart, Tracking Gant and Task Sheet views.
What does the “Delete Task” functionality do?
Question Link
Answer
The “Delete Tasks” functionality, as the name describes it, allow the possibility of erasing a task from a project.
What does the “Set Task Duration” functionality do?
Question Link
Answer
The “Set Task Duration” functionality, as the name describes it, allows you to change the task duration.
What are the supported link types/dependencies?
Question Link
Answer
The supported link types are: Finish to Start (FS), Finish to Finish (FF), Start to Start (SS), Start to Finish (SF).
In what views can I add a note to a task?
Question Link
Answer
You can add a note to a task in Gantt Chart, Task Sheet and Tracking Gantt views.
How can I add a milestone?
Question Link
Answer
To set a task as a Milestone select the desired task - click on Task tab - Task Information - Advanced- check "Mark task as milestone" - click OK.
Is there a quick way to assign the same resources to all instances of a recurring task?
Question Link
Answer
To assign the same resources for all instances of a recurring task, enter the resource for one instance, then copy paste the Resource Name field for each instance. After you have inserted the resources for a couple of instances you can select multiple Resource Names fields and then copy/paste them.
Is it possible to create recurring task?
Question Link
Answer

To insert a recurring task in your project, on the View menu click Gantt Chart – select the row below where you want a new recurring task to appear – click on Insert - Recurring task option under Task menu.

In what views is allowed to insert tasks?
Question Link
Answer
Adding a task is allowed only in Gantt Chart, Tracking Gant and Task Sheet views.
How do I split a task?
Question Link
Answer

To split a task, go to menu Task-Split then drag and drop from a Gantt Bar in order to create a split in the middle of the bar.

How to change the duration of a split task?
Question Link
Answer
To change the duration of the entire split task (including all of its sections), type a new duration in the Duration field, also the duration can be adjust using drag and drop action on bar.
How can bar styles be changed for split tasks?
Question Link
Answer
By default, split tasks are represented in the Gantt Chart view with dotted lines connecting each split portion. You can change the appearance of the split by modifying the split bar style using Bar Style dialog.
How to remove split task section?
Question Link
Answer
To remove a split in a task (join), drag a section of the task until it touches another section
Does inserting a task affect the project schedule?
Question Link
Answer
Inserting a task in your project may affect your schedule and you may run into problems. If you insert a new task under a summary task, the new inserted task will be a subtask. After you insert a task, the application automatically renumbers the tasks.
Can task types be used to change the hierarchical structure of a task?
Question Link
Answer
In order to change the hierarchical structure of a task or subtask as part of an outline structure for your project, you need to indent or outdent the task rather than change the task type or add a deadline date.
What is Fixed Duration Task Type?
Question Link
Answer
Fixed Duration Task Type applies to a task in which the duration is a fixed value and any changes to the work or the assigned units (that is, resources) don't affect the task's duration.