What is Enterprise Task Outline Code1-30 field?
Question Link
Answer
The Enterprise Task Outline Code1 through Enterprise Task Outline Code30 fields contain an alphanumeric code that represents a flat list or hierarchical structure of tasks (for example, cost accounting codes associated with tasks).
What is Enterprise Resource Outline Code1-29 field?
Question Link
Answer
The Enterprise Resource Outline Code1 through Enterprise Resource Outline Code29 fields contain an alphanumeric code that represents a flat list or hierarchical structure of resources (for example, skill codes or job codes).
What is Enterprise Required Values field?
Question Link
Answer
The Enterprise Required Values field indicates whether the resource has the necessary required values for Project Server 2013.
What is Enterprise Number1-40 field?
Question Link
Answer
The Enterprise Project Number1 through Enterprise Project Number40 fields can store any custom project number information as defined by your project management administrator or other user who has administrative permissions.
What is Enterprise Flag1-20 field?
Question Link
Answer
The Enterprise Flag1 through Enterprise Flag20 fields can store any custom task, resource, or assignment flag information as defined by your project management administrator or other user who has administrative permissions.
What is Enterprise field?
Question Link
Answer
The Enterprise field shows whether a resource is from the enterprise resource pool (Yes) or the local resource pool (No).
What is Enterprise Duration1-10 field?
Question Link
Answer
The Enterprise Duration1 through Enterprise Duration10 fields can store any custom task, resource, or assignment duration information as defined by your project management administrator or other user who has administrative permissions.
What is Enterprise Date1-30 field?
Question Link
Answer
The Enterprise Date1 through Enterprise Date30 fields can store any custom task, resource, or assignment date information as defined by your project management administrator or other user who has administrative permissions.
What is Enterprise Cost1-10 field?
Question Link
Answer
The Enterprise Cost1 through Enterprise Cost10 fields can store any custom task, resource, or assignment cost information as defined by your project management administrator or other user who has administrative permissions.
What is Enterprise Base Calendar field?
Question Link
Answer
The Enterprise Base Calendar field indicates whether the resource is assigned to a base calendar from the enterprise global template.
What is E-mail Address field?
Question Link
Answer
The E-mail Address field contains the e-mail address of a resource.
What is Effort Driven field?
Question Link
Answer
The Effort Driven field indicates whether the scheduling for the task is effort-driven scheduling.
What is Earned Value Method field?
Question Link
Answer
The Earned Value Method field provides choices for whether the % Complete or Physical % Complete field should be used to calculate budgeted cost of work performed (BCWP).
What is Early Start field?
Question Link
Answer
The Early Start field contains the earliest date that a task could possibly begin, based on the early start dates of predecessor and successor tasks and other constraints.
What is Early Finish field?
Question Link
Answer
The Early Finish field contains the earliest date that a task could possibly finish, based on early finish dates of predecessor and successor tasks, other constraints, and any leveling delay.
What is EAC field?
Question Link
Answer
The EAC (estimate at completion) field shows the expected total cost of a task based on performance up to the status date.
What is Duration1-10 field?
Question Link
Answer
The Duration1 through Duration10 fields store any task, resource, or assignment duration information.
What is Duration Variance field?
Question Link
Answer
The Duration Variance field contains the difference between the baseline duration of a task and the total duration (current estimate) of a task.
What is Duration field?
Question Link
Answer
The Duration field shows the total span of active working time for a task.
What is Deliverable Type field?
Question Link
Answer
The Deliverable Type field indicates whether the current task has an associated deliverable, and whether that deliverable is produced by the current task or produced by a separate project or task upon which the current task is dependent.
What is Deliverable Start field?
Question Link
Answer
For each task that has a deliverable associated with it, the Deliverable Start field displays the scheduled start date of that deliverable.
What is Deliverable Name field?
Question Link
Answer
For each task that has a deliverable associated with it, the Deliverable Name field displays the name or title of that deliverable.
What is Deliverable GUID field?
Question Link
Answer
For each task that has a deliverable associated with it, the Deliverable GUID field displays the globally unique identifier (GUID) for that deliverable.
What is Deliverable Finish field?
Question Link
Answer
For each task that has a deliverable associated with it, the Deliverable Finish field displays the scheduled finish date of that deliverable.
What is Default Assignment Owner field?
Question Link
Answer
The Default Assignment Owner field contains the name of the enterprise user who is responsible for entering status on a given assignment.