Can I reschedule uncompleted work only for selected tasks in a project?
Can I reschedule uncompleted work only for selected tasks in a project?
Question Link
Question Link
Answer
You can reschedule uncompleted work only for Selected tasks by going to menu Project – Update Project, select the “Reschedule uncompleted work to start after” and select a date from the date picker. From the “For:” section check the “Selected tasks” checkbox and click OK.Note: If you don't specify a date, Project Plan 365 uses the current or status date.
Can I update only selected tasks from a project?
Can I update only selected tasks from a project?
Question Link
Question Link
Answer
You can update only Selected tasks from a project by going to menu Project – Update Project, select the “Set 0% - 100% complete” or “Set 0% or 100% complete only” option under the “Update work as complete through:” and select a date from the date picker. From the “For:” section check the “Selected tasks” checkbox and click OK.Note: If you don't specify a date, Project Plan 365 uses the current or status date.
How can I reschedule uncompleted work in a project?
How can I reschedule uncompleted work in a project?
Question Link
Question Link
Answer
To reschedule uncompleted work in your project, go to menu Project – Update Project, check “Reschedule uncompleted work to start after” option, select a date from the date picker then click OK. All tasks will be updated and uncompleted / unstated work will be rescheduled.Note: If you don't specify a date, Project Plan 365 uses the current or status date.
How can I update the entire project with 0% or 100% complete only?
How can I update the entire project with 0% or 100% complete only?
Question Link
Question Link
Answer
To update your project with 0% or 100% complete only, go to menu Project – Update Project, make sure the “Set 0% or 100% complete only” option is checked under the “Update work as complete through:” section, select a date from the date picker and click OK.Note: If you don't specify a date, Project Plan 365 uses the current or status date.
How can I update the entire project with any %Complete?
How can I update the entire project with any %Complete?
Question Link
Question Link
Answer
To update the project with any %Complete, go to menu Project – Update Project, make sure the “Set 0% - 100% complete” option is checked under the “Update work as complete through:” section, select a date from the date picker and click OK.Note: If you don't specify a date, Project Plan 365 uses the current or status date.
Where can I find the Update Project functionality?
Where can I find the Update Project functionality?
Question Link
Question Link
What is the Update Project functionality?
What is the Update Project functionality?
Question Link
Question Link
Can I set the Deadline for the entire project?
On what platforms can I set Project Task Status Method?
On what platforms can I set Project Task Status Method?
Question Link
Question Link
Is the “Share” functionality also available in the Project Plan 365 for iPhone app?
Is the "Share" functionality also available in the Project Plan 365 for iPhone app?
Question Link
Question Link
Why isn’t the “Task Status Method” field available in my Options dialog?
Why isn’t the “Task Status Method” field available in my Options dialog?
Question Link
Question Link
Answer
If the Task Status Method field isn’t available in the Project Plan 365 application, please make sure you have the latest version of the application installed on your device: Download
What does the “Help” button inside the “Update Task Status Method” dialog do?
What does the “Help” button inside the “Update Task Status Method” dialog do?
Question Link
Question Link
What do the Project Status values represent?
What do the Project Status values represent?
Question Link
Question Link
Answer
The Project Status indicates the current status of your project: Complete, On Schedule, Late, Future, On Budget or Overbudget:
- Complete – If the project is 100% complete, then our application sets the Project Status to Complete.
- On Schedule – If percent complete is spread to at least the day before the status date, then the Project Status is On Schedule.
- Late – If percent complete does not reach midnight on the day before the status date, then the Project Status is Late.
- Future – If the Start Date of the project is greater than the Status Date, then the Project Status is set to Future.
- On Budget – If the project total cost is less or the same amount as the set project maximum cost, then the Project Status is set to On Budget.
- Overbudget – If the project total cost is over the set project maximum cost, then the Project Status is set to Overbudget.
Why does the task status not contain budget information?
Why does the task status not contain budget information?
Question Link
Question Link
How can I check if a task in on budget?
How can I check if a task in on budget?
Question Link
Question Link
How can I check if a task status is complete?
How can I check if a task status is complete?
Question Link
Question Link
How can I check if a task status is future?
How can I check if a task status is future?
Question Link
Question Link
How can I check if a task status is late?
How can I check if a task status is late?
Question Link
Question Link
How can I check if a task status is on schedule?
How can I check if a task status is on schedule?
Question Link
Question Link
Can I set the Task Status Method for all my organization projects?
Can I set the Task Status Method for all my organization projects?
Question Link
Question Link
Answer
To set the Task Status Method for all your organization projects, go to menu File – Account – Organization Information – Global Settings – Schedule Tab and from the Task Status Method field select the desired method. Learn more about Global Settings functionality.
Note: To have these settings applied to all your organization projects, make sure you create projects using the New blank project using Global Settings or New Blank Project Using Global Settings options from Home / New menu.
How can I see the status of all tasks in my project?
How can I see the status of all tasks in my project?
Question Link
Question Link
Answer
To see the status of all tasks in your project, in the Gantt Chart View or any other View with grids, add the Status column by going to menu Format– Insert Column, select Status and click OK.
Or you can apply the Status table by going to menu Project – Tables – More Tables, select the Status table and click Apply.
Or you can apply the Status table by going to menu Project – Tables – More Tables, select the Status table and click Apply.
How can I see the status of the entire project?
How can I see the status of the entire project?
Question Link
Question Link
Can I have different tasks with different Task Status Methods?
Can I have different tasks with different Task Status Methods?
Question Link
Question Link
How do I know if a task is late?
How do I know if a task is late?
Question Link
Question Link
How do I know if a task is over budget?
How do I know if a task is over budget?
Question Link
Question Link