To insert multiple resources, select multiple consecutive rows using either CTRL or SHIFT keys on your keyboard and then press on Insert key or use the New Resource option from the contextual menu to insert multiple resources at a time. These resources will be positioned above the selected rows in the resources list. The number of newly inserted resources will be equal to the number of selected rows.
Question Link
Question Link
To delete multiple resources, select multiple consecutive rows using either CTRL or SHIFT keys on your keyboard and then click on Delete option from the Team menu, or press on Delete key or use the Delete Resource option from the contextual menu to delete multiple resources at a time. The IDs of the remaining resources will be automatically renumbered.
Question Link
There are 3 ways to assign resources to a task:
1. Using the Resource Name column - just write or select the resource/resources you want to add. Set the units or the number of items.
2. Using Task Information - Resource tab - select resources and write or select the resource/resources you want to add. Set the units or the number of items.
3. Using menu Team - Assign. Right click on a task in the grid and select Assign then select your resource and click on the Assign button.
Question Link
Question Link
Question Link
Question Link
Question Link
Question Link
To enter a per-use cost resource click View - Resource Sheet. In the entry table click on column Type select Cost. After this, assign that resource of type cost to a task using the Task Information dialog. In Resources tab select the cost resource and enter the cost, then click on the OK button.
Question Link
Question Link
Question Link
Question Link
Question Link
Question Link
Question Link
Question Link
Question Link
Question Link
Project Plan 365 app will not move your task automatically if you have the same resource on two parallel tasks.
The application tells you that you have an overallocated resource by making the entire resource font with red in Resource Sheet view.
If you want tasks to be in sequence, you need to link the tasks and specify a predecessor.
Question Link
Question Link
Question Link
Question Link
With contextual New Resource option allows you to insert a resource at any position in the list of resources from your project: either on top of the list, in the middle or at the bottom the list. In case you select a row in Resource Sheet and press Insert option the newly added resource will be inserted in the resource list above the selected row.