Browse by Category
Question Link
A resource is overallocated when it is assigned too much work to complete within the resource's available time. You can resolve resource overallocation by adjusting either tasks or resources in your project. For detailed information about Resource Overallocation, see the Resource Overallocation Online Help Article.
Question Link
To level tasks for certain resources, go to “Team” menu and click the “Level Resource” button. In the “Level Resources” dialog, select the resources for which you want to level tasks and click the “OK” button. A summary of how Project Plan 365 fixed the overallocation will be displayed. Click the “OK” button for the changes to be applied. For detailed information about Resource Leveling, see the Resource Leveling Online Help Article.
Question Link
To level only the selected tasks, go to “Team” menu and click the “Level All” button. In the “Resource Leveling” dialog, the “Selected tasks” option and click the “OK” button. A summary of how Project Plan 365 fixed the overallocation will be displayed. Click the “OK” button for the changes to be applied. For detailed information about Resource Leveling, see the Resource Leveling Online Help Article.
Question Link
To level the entire project, go to “Team” menu and click the “Level All” button. In the “Resource Leveling” dialog, the “Entire Project” option and click the “OK” button. A summary of how Project Plan 365 fixed the overallocation will be displayed. Click the “OK” button for the changes to be applied. For detailed information about Resource Leveling, see the Resource Leveling Online Help Article.
Question Link
Use resource leveling technique to resolve resource overallocation in tasks. Project Plan 365 evaluates resource allocations and adjusts your plans so that your resources are not overallocated. For detailed information about Resource Leveling, see the Resource Leveling Online Help Article.
Question Link
Resource leveling is a technique in which start and finish dates are adjusted based on resource limitation with the goal of balancing demand for resources with the available supply. For detailed information about Resource Leveling, see the Resource Leveling Online Help Article.
Question Link
Yes. Project Plan 365 can automatically resolve resource overallocations using Resource Leveling. For detailed information about automatic leveling, see the Resource Leveling Online Help Article.
Question Link
If you want to resolve resource overallocations manually, you can adjust task scheduling, resource assignments, working time, or assignment units. For detailed information about diagnosing and manually resolving overallocations, see the Resource Overallocation Online Help Article.
Question Link
The “Set Task Mode” functionality gives you the option of deciding how much control you want over task scheduling in a project. The Task Mode field indicates whether a task is scheduled manually or automatically scheduled. The default scheduling mode for new tasks is configurable in File > Options > Schedule.
Question Link
Question Link
Question Link
Question Link
You can access Erix.AI Create Project from multiple locations within Project Plan 365, including:
- Right after creating an account and starting a trial you will get the option to create a new project using Erix.AI.
- By going to menu File – New – click on Create project with Erix.AI.
- Directly from the Erix conversation by clicking on Chat with Erix button from the Quick Access Toolbar then asking Erix.AI to create a project.
- Directly from the Create Project with Erix.AI Landing Page: https://projectplan365.com/create-project-with-erix-ai
Question Link
Question Link
Question Link
Question Link
Question Link
Eix AI is currently available on our Windows, Mac and Web platform.
To access the Web Platform please go to the following link: https://online.projectplan365.com/projectviewernow/tViews.aspx
Note: The Create your first project with Erix.AI functionality is available on Windows and Mac platforms.
Question Link
You can create a project from scratch with Erix.AI. Simply ask Erix.AI to “Create plan” and it will provide 2 options. Click on the “Create Project with Erix.AI” button and the generation flow will begin. For more information, please check the Erix AI Create Project Online Help Article.
Question Link
You can ask Erix AI any question about project management by clicking on the Chat with Erix button from the Quick Access Toolbar. Either click on a conversation starter from the center section or type in a question about project management (e.g., What is a milestone?)
Note: Click here to view what questions are supported by Erix AI.
Question Link
You can ask Erix AI questions about email generating queries, first open the desired project. Click on the Chat with Erix button from the Quick Access Toolbar. Either click on a conversation starter from the center section or type in a question about email generating queries (e.g., Generate an email about project status.)
Note: Click here to view what questions are supported by Erix AI.
Question Link
You can ask Erix AI questions about cash flow and budget, first open the desired project. Click on the Chat with Erix button from the Quick Access Toolbar. Either click on a conversation starter from the center section or type in a question about cash flow and budget (e.g., What is the total cost for tasks scheduled this week?)
Note: Click here to view what questions are supported by Erix AI.
Question Link
You can ask Erix AI questions about resource usage, first open the desired project. Click on the Chat with Erix button from the Quick Access Toolbar. Either click on a conversation starter from the center section or type in a question about resource usage (e.g., What tasks is [resource_name] working on?)
Note: Erix AI can show only 5 resources/tasks per answer, to see the full list of resources, ask Erix AI to show them by typing in “Show next tasks” and press Enter.
Note: Click here to view what questions are supported by Erix AI.
Question Link
You can ask Erix AI questions about resource status, first open the desired project. Click on the Chat with Erix button from the Quick Access Toolbar. Either click on a conversation starter from the center section or type in a question about resource status (e.g., What resources are overallocated?
Note: Erix AI can show only 5 resources per answer, to see the full list of resources, ask Erix AI to show them by typing in “Show next tasks” and press Enter.
Note: Click here to view what questions are supported by Erix AI.
Question Link
You can ask Erix AI questions about task status, first open the desired project. Click on the Chat with Erix button from the Quick Access Toolbar. Either click on a conversation starter from the center section or type in a question about task status (e.g., What tasks are late?)
Note: Erix AI can show only 5 tasks per answer, to see the full list of tasks, ask Erix AI to show them by typing in “Show next tasks” and press Enter.